United States › Grid › Interconnection queues › Florida
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Florida (2018 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project IC-758, Bay County Gas |
741 MW | Withdrawn / abandoned |
| Solar project IC-712, Calhoun County Solar |
350 MW | Withdrawn / abandoned |
| Solar project IC-669, Calhoun County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 49, Hillsborough County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project 50, Polk County Solar |
75.0 MW | Withdrawn / abandoned |
| Solar project IC-680, Santa Rosa County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 231, Alachua County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 214, Suwannee County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 213, Suwannee County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 218C, Gilchrist County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 223, Suwannee County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 215, Alachua County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 224, Suwannee County Solar · Patchwork Solar, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 216, Alachua County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 232C, Marion County Solar · Leeward Renewable Energy, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 220, Madison County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project 219, Madison County Solar · Marsh Solar, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 234, Citrus County Solar · Duke Energy Florida, LLC |
74.9 MW | Withdrawn / abandoned |
| Solar project 212, Jefferson County Solar · Masked |
74.9 MW | Withdrawn / abandoned |
| Solar project IC-668, Jackson County Solar |
74.9 MW | Withdrawn / abandoned |
| Solar project 348, Putnam County Solar · FPL |
74.5 MW | Withdrawn / abandoned |
| Solar project 239, Citrus County Solar · Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 21 Solar |
74.5 MW | Withdrawn / abandoned |
| Withdrawn Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project 230, Hardee County Solar · Masked |
74.5 MW | Withdrawn / abandoned |
| Solar + storage project 346, Bradford County Solar + storage · Third Party |
74.5 MW | Withdrawn / abandoned |
| Solar project 227, Polk County Solar · Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 363, Manatee County Solar · FPL |
74.5 MW | Withdrawn / abandoned |
| Solar project 226, Osceola County Solar · Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 43, Polk County Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project IC-745, Calhoun County Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project 228, Polk County Solar · Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 45, Manatee County Solar |
74.5 MW | Withdrawn / abandoned |
| Solar + storage project 354, Putnam County Solar + storage · Third Party |
74.5 MW | Withdrawn / abandoned |
| Solar project 24 Solar |
74.5 MW | Withdrawn / abandoned |
| Solar + storage project 330, Flagler County Solar + storage · Third Party |
74.5 MW | Withdrawn / abandoned |
| Solar project IC-714, Gadsden County Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project 217, Madison County Solar · Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 241, Alachua County Solar · Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 225, Levy County Solar · Florida Renewable Partners, LLC |
74.5 MW | Withdrawn / abandoned |
| Solar project 360, Nassau County Solar · FPL |
74.5 MW | Withdrawn / abandoned |
| Solar project IC-744, Calhoun County Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project 26 Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project 44A, Manatee County Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project 238, Taylor County Solar · Fresh Air Energy II, LLC |
74.5 MW | Withdrawn / abandoned |
| Solar project 25 Solar |
74.5 MW | Withdrawn / abandoned |
| Solar + storage project 329, St Johns County Solar + storage · Third Party |
74.5 MW | Withdrawn / abandoned |
| Solar project IC-708, Jackson County Solar |
74.5 MW | Withdrawn / abandoned |
| Solar project 229, Hardee County Solar · Masked |
74.5 MW | Withdrawn / abandoned |
| Solar project 23 Solar |
74.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)