πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project 330, Flagler County

Solar + storage project 330, Flagler County is a 74.5 MW solar + storage request withdrawn in the Southeast interconnection queue, in Flagler County, Florida, connecting to Florida Power & Light.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2018 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. OperatingDec 2023 (not reached)
  6. Closed (not reached)

Request details

Queue ID
330
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
Third Party
Connection point (POI)
Korona-Putnam 230kV
Location
Flagler County, Florida
Technology
Solar: 74.5 MW Β· Battery
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Withdrawn
Entered queue
30 January 2018
Proposed online date
December 2023
Came online
December 2023

Location

Marker shows the centre of Flagler County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem