United States โ€บ Grid โ€บ Interconnection queues โ€บ Florida

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Florida (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown388,979 MW
Active in queue224 MW3 requests
Agreement signed0.0 MW0 requests
Withdrawn388,979 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

38 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 16
Gas
1,190 MWWithdrawn / abandoned FLSoutheast May 2016target 2020
Gas project 143, Volusia County
Gas ยท Masked
1,180 MWWithdrawn / abandoned Volusia, FLSoutheast May 2016target 2021
Gas project 157, Volusia County
Gas ยท Masked
1,174 MWWithdrawn / abandoned Volusia, FLSoutheast Sep 2016target 2021
Gas project 19
Gas
655 MWWithdrawn / abandoned FLSoutheast Aug 2016target 2020
Gas project 156, Volusia County
Gas ยท Masked
655 MWWithdrawn / abandoned Volusia, FLSoutheast Sep 2016target 2021
Solar project 142, Osceola County
Solar ยท Masked
617 MWWithdrawn / abandoned Osceola, FLSoutheast May 2016target 2018
Gas project 13
Gas
609 MWWithdrawn / abandoned FLSoutheast Mar 2016target 2021
Other project 144, Sumter County
Other ยท Masked
560 MWWithdrawn / abandoned Sumter, FLSoutheast May 2016target 2021
Solar project IC-444, Jackson County
Solar
295 MWWithdrawn / abandoned Jackson, FLSoutheast Mar 2016
Solar project IC-442, Jackson County
Solar
213 MWWithdrawn / abandoned Jackson, FLSoutheast Feb 2016
Solar project IC-567, Holmes County
Solar
80.0 MWWithdrawn / abandoned Holmes, FLSoutheast Dec 2016
Solar project 140, Alachua County
Solar ยท Masked
75.0 MWWithdrawn / abandoned Alachua, FLSoutheast May 2016target 2021
Solar project 147A, Alachua County
Solar ยท Masked
74.9 MWWithdrawn / abandoned Alachua, FLSoutheast May 2016target 2019
Solar project 150, Hardee County
Solar ยท Masked
74.9 MWWithdrawn / abandoned Hardee, FLSoutheast Jun 2016target 2019
Solar project 138B, Bradford County
Solar ยท Masked
74.9 MWWithdrawn / abandoned Bradford, FLSoutheast Apr 2016target 2019
Solar project 138A, Hamilton County
Solar ยท Masked
74.9 MWWithdrawn / abandoned Hamilton, FLSoutheast Apr 2016target 2019
Solar project 138C, Highlands County
Solar ยท Masked
74.9 MWWithdrawn / abandoned Highlands, FLSoutheast Apr 2016target 2019
Solar project IC-558, Jackson County
Solar
74.9 MWWithdrawn / abandoned Jackson, FLSoutheast Dec 2016
Solar project 153, Columbia County
Solar ยท Penholoway Solar, LLC
74.9 MWWithdrawn / abandoned Columbia, FLSoutheast Jul 2016target 2019
Solar project 139, Gilcrhist County
Solar ยท Masked
74.9 MWWithdrawn / abandoned Gilcrhist, FLSoutheast Apr 2016target 2018
Solar project 159, Hamilton County
Solar ยท Duke Energy Florida, LLC
74.9 MWWithdrawn / abandoned Hamilton, FLSoutheast Sep 2016target 2020
Solar project 146, Polk County
Solar ยท Masked
74.8 MWWithdrawn / abandoned Polk, FLSoutheast May 2016target 2020
Solar project 145, Polk County
Solar ยท Masked
74.8 MWWithdrawn / abandoned Polk, FLSoutheast May 2016target 2020
Solar project 165, Osceola County
Solar ยท Florida Renewable Partners, LLC
74.5 MWWithdrawn / abandoned Osceola, FLSoutheast Dec 2016target 2021
Solar project 17
Solar
74.5 MWWithdrawn / abandoned FLSoutheast May 2016target 2019
Solar project 167, Hamilton County
Solar ยท Masked
74.5 MWWithdrawn / abandoned Hamilton, FLSoutheast Dec 2016target 2018
Solar project 166, Hamilton County
Solar ยท Florida Renewable Partners, LLC
74.5 MWWithdrawn / abandoned Hamilton, FLSoutheast Dec 2016target 2021
Solar project 192, Manatee County
Solar ยท FPL
74.5 MWWithdrawn / abandoned Manatee, FLSoutheast May 2016target 2027
Solar project 170, Columbia County
Solar ยท Masked
74.5 MWWithdrawn / abandoned Columbia, FLSoutheast Dec 2016target 2018
Solar project IC-482, Jackson County
Solar
74.5 MWWithdrawn / abandoned Jackson, FLSoutheast Aug 2016
Solar project 212, Baker County
Solar ยท FPL
60.0 MWWithdrawn / abandoned Baker, FLSoutheast Oct 2016target 2025
Solar project 18
Solar
52.8 MWWithdrawn / abandoned FLSoutheast May 2016target 2020
Solar project 141, Citrus County
Solar ยท Masked
50.0 MWWithdrawn / abandoned Citrus, FLSoutheast May 2016target 2021
Solar project 168, Hamilton County
Solar ยท Masked
40.0 MWWithdrawn / abandoned Hamilton, FLSoutheast Dec 2016target 2021
Solar project 155A, Jefferson County
Solar ยท Masked
35.0 MWWithdrawn / abandoned Jefferson, FLSoutheast Aug 2016target 2017
Solar project 172, Gilchrist County
Solar ยท Masked
34.0 MWWithdrawn / abandoned Gilchrist, FLSoutheast Dec 2016target 2021
Solar project 159B, Hamilton County
Solar ยท Masked
30.0 MWWithdrawn / abandoned Hamilton, FLSoutheast Oct 2016target 2021
Solar project 155B, Gilchrist County
Solar ยท Masked
30.0 MWWithdrawn / abandoned Gilchrist, FLSoutheast Aug 2016target 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)