United States βΊ Grid βΊ Interconnection queues βΊ Florida
GAS Β· SOUTHEASTGas project 19
Gas project 19 is a 655 MW gas request withdrawn in the Southeast interconnection queue, connecting to Seminole Electric Cooperative.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2016 (completed)
- Withdrawn / abandonedOct 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 19
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Seminole Electric Cooperative
- Connection point (POI)
- SGS Switchyard
- Location
- Florida
- Technology
- Gas: 655 MW
- Total requested
- 655 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: System Impact; Status: Withdrawn by Customer on 10/06/2017
- Queue status
- Withdrawn
- Entered queue
- 22 August 2016
- Proposed online date
- September 2020
- Withdrawn
- October 2017
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem