United States โ€บ Grid โ€บ Interconnection queues โ€บ Colorado

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Colorado (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5914.0 GW
Active in queue14.0 GW59 requests
Agreement signed666 MW3 requests
Withdrawn5566 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

59 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 5RSC-2024-17, Kit Carson County
Onshore wind
603 MWIn study Kit Carson, COWest Jan 2024target 2026
Onshore wind project 5RSC-2024-29, Yuma County
Onshore wind
554 MWIn study Yuma, COWest Jan 2024target 2027
Solar project 5RSC-2024-22, Crowley County
Solar
500 MWIn study Crowley, COWest Jan 2024target 2027
Solar + storage project GI-2024-06, Morgan County
Solar + storage
500 MWIn study Morgan, COWest May 2024target 2027
Onshore wind project 5RSC-2024-15, Kiowa County
Onshore wind
500 MWIn study Kiowa, COWest Jan 2024target 2027
Onshore wind project 5RSC-2024-28, Kit Carson County
Onshore wind
500 MWIn study Kit Carson, COWest Jan 2024target 2025
Onshore wind project 5RSC-2024-16, Cheyenne County
Onshore wind
450 MWIn study Cheyenne, COWest Jan 2024target 2026
Onshore wind project GI-2024-13, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Onshore wind project GI-2024-12, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Solar + storage project GI-2024-05, Pueblo County
Solar + storage
400 MWIn study Pueblo, COWest Apr 2024target 2028
Gas project 5RSC-2024-02, Weld County
Gas
400 MWIn study Weld, COWest Jan 2024target 2027
Solar project 5RSC-2024-21, Crowley County
Solar
400 MWIn study Crowley, COWest Jan 2024target 2029
Solar + storage project GI-TC-2024-30, Morgan County
Solar + storage
400 MWAgreement signed Morgan, COWest May 2024target 2028
Solar + storage project GI-TC-2024-31, Elbert County
Solar + storage
398 MWIn study Elbert, COWest May 2024target 2028
Onshore wind project GI-TC-2024-25, Weld County
Onshore wind
350 MWIn study Weld, COWest May 2024target 2028
Solar + storage project 5RSC-2024-06, Pueblo County
Solar + storage
300 MWIn study Pueblo, COWest Jan 2024target 2028
Onshore wind project 5RSC-2024-18, Prowers County
Onshore wind
293 MWIn study Prowers, COWest Jan 2024target 2029
Battery storage project 5RSC-2024-11, Morgan County
Battery storage
250 MWIn study Morgan, COWest Jan 2024target 2027
Solar + storage project GI-2024-16, Kiowa County
Solar + storage
250 MWIn study Kiowa, COWest May 2024target 2027
Solar + storage project 5RSC-2024-27, Morgan County
Solar + storage
250 MWIn study Morgan, COWest Jan 2024target 2026
Battery storage project 5RSC-2024-10, Cheyenne County
Battery storage
250 MWIn study Cheyenne, COWest Jan 2024target 2027
Solar project GI-TC-2024-17, Kit Carson County
Solar
225 MWIn study Kit Carson, COWest May 2024target 2030
Battery storage project 5RSC-2024-12, Pueblo County
Battery storage
200 MWIn study Pueblo, COWest Jan 2024target 2027
Battery storage project 5RSC-2024-09, Park County
Battery storage
200 MWIn study Park, COWest Jan 2024target 2027
Gas project 5RSC-2024-01, Weld County
Gas
200 MWIn study Weld, COWest Jan 2024target 2027
Solar project 5RSC-2024-23, Pueblo County
Solar
200 MWIn study Pueblo, COWest Jan 2024target 2028
Solar project BHCT G49, Pueblo County
Solar
200 MWIn study Pueblo, COWest Jun 2024target 2026
Solar + storage project GI-2024-01, Weld County
Solar + storage
199 MWIn study Weld, COWest Apr 2024target 2027
Solar + storage project 5RSC-2024-24, Adams County
Solar + storage
199 MWIn study Adams, COWest Jan 2024target 2027
Solar + storage project GI-2024-20, Lincoln County
Solar + storage
199 MWIn study Lincoln, COWest May 2024target 2028
Battery storage project GI-2024-09, Adams County
Battery storage
199 MWIn study Adams, COWest May 2024target 2027
Solar + storage project GI-2024-19, Lincoln County
Solar + storage
199 MWIn study Lincoln, COWest May 2024target 2028
Solar + storage project GI-2024-02, Weld County
Solar + storage
199 MWIn study Weld, COWest Apr 2024target 2027
Battery storage project 5RSC-2024-13, Weld County
Battery storage
199 MWIn study Weld, COWest Jan 2024target 2027
Solar project GI-TC-2024-10, Kit Carson County
Solar
199 MWIn study Kit Carson, COWest May 2024target 2028
Onshore wind project GI-TC-2024-12, Yuma County
Onshore wind
170 MWIn study Yuma, COWest May 2024target 2027
Solar + storage project GI-2024-11, Saguache County
Solar + storage
170 MWIn study Saguache, COWest May 2024target 2028
Onshore wind project GI-TC-2024-29, Kit Carson County
Onshore wind
170 MWIn study Kit Carson, COWest May 2024target 2028
Onshore wind project GI-TC-2024-11, Kit Carson County
Onshore wind
167 MWAgreement signed Kit Carson, COWest May 2024target 2027
Solar + storage project GI-TC-2024-02, Lincoln County
Solar + storage
150 MWIn study Lincoln, COWest Apr 2024target 2028
Solar project GI-2024-03, Adams County
Solar
150 MWIn study Adams, COWest Apr 2024target 2029
Solar + storage project GI-2024-14, Pueblo County
Solar + storage
150 MWIn study Pueblo, COWest May 2024target 2027
Solar + storage project GI-TC-2024-01, Lincoln County
Solar + storage
150 MWIn study Lincoln, COWest Apr 2024target 2027
Solar project GI-2024-18, Morgan County
Solar
150 MWIn study Morgan, COWest May 2024target 2027
Solar project GI-TC-2024-22, Weld County
Solar
140 MWIn study Weld, COWest May 2024target 2028
Battery storage project 24-03011, Larimer County
Battery storage
130 MWIn study Larimer, COWest Mar 2024target 2027
Solar + storage project GI-TC-2024-21, Montezuma County
Solar + storage
125 MWIn study Montezuma, COWest May 2024target 2028
Solar project GI-2024-10, Adams County
Solar
120 MWIn study Adams, COWest May 2024target 2027
Solar + storage project GI-2024-15, Alamosa County
Solar + storage
110 MWIn study Alamosa, COWest May 2024target 2028
Battery storage project GI-TC-2024-19, Montrose County
Battery storage
100 MWAgreement signed Montrose, COWest May 2024target 2027
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)