SOLAR + STORAGE · WESTSolar + storage project GI-2024-11, Saguache County
Solar + storage project GI-2024-11, Saguache County is a 170 MW solar + storage request in interconnection study in the West interconnection queue, in Saguache County, Colorado, connecting to Public Service Company Of Colorado.
- PlanningQueued May 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GI-2024-11
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Poncha-San Luis Valley 230 kV line
- Location
- Saguache County, Colorado
- Technology
- Solar: 170 MW · Battery
- Total requested
- 170 MW
- Service type
- Energy only (ERIS)
- Study phase
- Detailed status: Study to be started after completion of 5RSC
- Queue status
- Active
- Entered queue
- 17 May 2024
- Proposed online date
- May 2028
Location
Marker shows the centre of Saguache County; the queue data does not give exact sites.
Other requests in Saguache County
- Solar project GI-2008-32, Saguache CountySolar · 250 MW · withdrawn
- Solar project GI-2008-21, Saguache CountySolar · 200 MW · withdrawn
- Solar project GI-2009-1, Saguache CountySolar · 200 MW · withdrawn
- Solar + storage project GI-2023-11, Saguache CountySolar + storage · 170 MW · withdrawn
- Solar project GI-2009-10, Saguache CountySolar · 150 MW · withdrawn
- Solar project GI-2008-26, Saguache CountySolar · 100 MW · withdrawn
- Solar project GI-2008-28, Saguache CountySolar · 100 MW · withdrawn
- Solar project GI-2008-27, Saguache CountySolar · 100 MW · withdrawn
- Solar project GI-2008-20, Saguache CountySolar · 100 MW · withdrawn
- Solar project GI-2016-26, Saguache CountySolar · 50.0 MW · withdrawn
- Solar project GI-2010-14, Saguache CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem