United States βΊ Grid βΊ Interconnection queues βΊ Colorado
SOLAR Β· WESTSolar project GI-2008-20, Saguache County
Solar project GI-2008-20, Saguache County is a 100 MW solar request withdrawn in the West interconnection queue, in Saguache County, Colorado, connecting to Public Service Company Of Colorado.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2008 (completed)
- Withdrawn / abandonedJan 2011 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-2008-20
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- San Luis Substation
- Location
- Saguache County, Colorado
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- System Impact Study underway Request Withdrawn 1/13/11
- Queue status
- Withdrawn
- Entered queue
- 9 October 2008
- Proposed online date
- August 2011
- Withdrawn
- January 2011
Location
Marker shows the centre of Saguache County; the queue data does not give exact sites.
Other requests in Saguache County
- Solar + storage project GI-2024-11, Saguache CountySolar + storage Β· 170 MW Β· in study
- Solar project GI-2008-32, Saguache CountySolar Β· 250 MW Β· withdrawn
- Solar project GI-2008-21, Saguache CountySolar Β· 200 MW Β· withdrawn
- Solar project GI-2009-1, Saguache CountySolar Β· 200 MW Β· withdrawn
- Solar + storage project GI-2023-11, Saguache CountySolar + storage Β· 170 MW Β· withdrawn
- Solar project GI-2009-10, Saguache CountySolar Β· 150 MW Β· withdrawn
- Solar project GI-2008-26, Saguache CountySolar Β· 100 MW Β· withdrawn
- Solar project GI-2008-28, Saguache CountySolar Β· 100 MW Β· withdrawn
- Solar project GI-2008-27, Saguache CountySolar Β· 100 MW Β· withdrawn
- Solar project GI-2016-26, Saguache CountySolar Β· 50.0 MW Β· withdrawn
- Solar project GI-2010-14, Saguache CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem