Solar + storage project Q2409, Navajo County Solar + storage |
2,626 MW | In study |
Navajo, AZ | West |
Feb 2024 | target 2028 |
Other project Q572, Riverside County Other |
1,300 MW | In study |
Riverside, CA | West |
May 2024 | target 2031 |
Battery storage project Q2405, Maricopa County Battery storage |
1,020 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2033 |
Battery storage project Q112, San Bernardino County Battery storage |
1,000 MW | In study |
San Bernardino, CA | West |
Oct 2024 | target 2028 |
Solar + storage project Q2417, Maricopa County Solar + storage |
843 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2028 |
Solar + storage project Q2412, Navajo County Solar + storage |
822 MW | In study |
Navajo, AZ | West |
Feb 2024 | target 2028 |
Gas project 174, Pima County Gas |
800 MW | In study |
Pima, AZ | West |
Jun 2024 | target 2027 |
Other project G1072, Lewis County Other |
667 MW | In study |
Lewis, WA | West |
Dec 2024 | target 2027 |
Onshore wind project 5RSC-2024-17, Kit Carson County Onshore wind |
603 MW | In study |
Kit Carson, CO | West |
Jan 2024 | target 2026 |
Solar + storage project Q2415, Maricopa County Solar + storage |
600 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2028 |
Other project Q561, Maricopa County Other |
600 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2029 |
Solar + storage project Q2406, Maricopa County Solar + storage |
565 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2029 |
Onshore wind project 5RSC-2024-29, Yuma County Onshore wind |
554 MW | In study |
Yuma, CO | West |
Jan 2024 | target 2027 |
Other project 2024-G4, Mohave County Other |
550 MW | In study |
Mohave, AZ | West |
Apr 2024 | target 2027 |
Solar project 5RSC-2024-22, Crowley County Solar |
500 MW | In study |
Crowley, CO | West |
Jan 2024 | target 2027 |
Battery storage project Q108, San Bernardino County Battery storage |
500 MW | In study |
San Bernardino, CA | West |
Jun 2024 | target 2028 |
Solar + storage project GI-2024-06, Morgan County Solar + storage |
500 MW | In study |
Morgan, CO | West |
May 2024 | target 2027 |
Battery storage project PIS087, Salt Lake County Battery storage |
500 MW | In study |
Salt Lake, UT | West |
Sep 2024 | target 2027 |
Other project Q564, Maricopa County Other |
500 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2028 |
Solar + storage project Q563, Pinal County Solar + storage |
500 MW | In study |
Pinal, AZ | West |
May 2024 | target 2028 |
Battery storage project 2024-MP2, Mohave County Battery storage |
500 MW | In study |
Mohave, AZ | West |
Jan 2024 | target 2028 |
Onshore wind project 5RSC-2024-15, Kiowa County Onshore wind |
500 MW | In study |
Kiowa, CO | West |
Jan 2024 | target 2027 |
Battery storage project Company QQ, Washoe County Battery storage |
500 MW | In study |
Washoe, NV | West |
Mar 2024 | target 2028 |
Solar + storage project NC5-010, Kane County Solar + storage |
500 MW | In study |
Kane, UT | West |
Mar 2024 | target 2028 |
Battery storage project 2024-MP1, Mohave County Battery storage |
500 MW | In study |
Mohave, AZ | West |
Jan 2024 | target 2028 |
Solar + storage project Q111, Clark County Solar + storage |
500 MW | In study |
Clark, NV | West |
Jun 2024 | target 2026 |
Onshore wind project 5RSC-2024-28, Kit Carson County Onshore wind |
500 MW | In study |
Kit Carson, CO | West |
Jan 2024 | target 2025 |
Onshore wind project 5RSC-2024-16, Cheyenne County Onshore wind |
450 MW | In study |
Cheyenne, CO | West |
Jan 2024 | target 2026 |
Other project Q567, Maricopa County Other |
450 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2028 |
Other project Q560, Maricopa County Other |
425 MW | In study |
Maricopa, AZ | West |
May 2024 | target 2028 |
Onshore wind project GI-2024-13, Adams County Onshore wind |
423 MW | In study |
Adams, CO | West |
May 2024 | target 2028 |
Onshore wind project GI-2024-12, Adams County Onshore wind |
423 MW | In study |
Adams, CO | West |
May 2024 | target 2028 |
Battery storage project Q2413, Pinal County Battery storage |
409 MW | In study |
Pinal, AZ | West |
Feb 2024 | target 2027 |
Solar + storage project GI-2024-05, Pueblo County Solar + storage |
400 MW | In study |
Pueblo, CO | West |
Apr 2024 | target 2028 |
Gas project 5RSC-2024-02, Weld County Gas |
400 MW | In study |
Weld, CO | West |
Jan 2024 | target 2027 |
Solar project 5RSC-2024-21, Crowley County Solar |
400 MW | In study |
Crowley, CO | West |
Jan 2024 | target 2029 |
Onshore wind project PIS089, Lincoln County Onshore wind |
400 MW | In study |
Lincoln, WY | West |
Oct 2024 | target 2028 |
Solar + storage project GI-TC-2024-30, Morgan County Solar + storage |
400 MW | Agreement signed |
Morgan, CO | West |
May 2024 | target 2028 |
Gas project Q2403, Maricopa County Gas |
398 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2028 |
Solar + storage project GI-TC-2024-31, Elbert County Solar + storage |
398 MW | In study |
Elbert, CO | West |
May 2024 | target 2028 |
Onshore wind project GI-TC-2024-25, Weld County Onshore wind |
350 MW | In study |
Weld, CO | West |
May 2024 | target 2028 |
Battery storage project S0026, Converse County Battery storage |
350 MW | In study |
Converse, WY | West |
Feb 2024 | target 2026 |
Other project Q553, Navajo County Other |
340 MW | In study |
Navajo, AZ | West |
May 2024 | target 2028 |
Battery storage project S0028, Converse County Battery storage |
320 MW | In study |
Converse, WY | West |
Feb 2024 | target 2026 |
Wind + storage project 2024-G7, Yavapai County Wind + storage |
313 MW | In study |
Yavapai, AZ | West |
Nov 2024 | target 2028 |
Onshore wind project 2024-G5, Mohave County Onshore wind |
300 MW | In study |
Mohave, AZ | West |
Aug 2024 | target 2029 |
Solar + storage project 5RSC-2024-06, Pueblo County Solar + storage |
300 MW | In study |
Pueblo, CO | West |
Jan 2024 | target 2028 |
Other project Q570, Yuma County Other |
300 MW | In study |
Yuma, AZ | West |
May 2024 | target 2028 |
Wind + storage project CS24-15, Lincoln County Wind + storage |
300 MW | Agreement signed |
Lincoln, WA | West |
Apr 2024 | target 2029 |
Solar + storage project Q2402, Maricopa County Solar + storage |
300 MW | In study |
Maricopa, AZ | West |
Feb 2024 | target 2027 |