Onshore wind project Q320, San Juan County Onshore wind |
1,500 MW | Paused / redesign |
San Juan, NM | West |
Sep 2019 | target 2026 |
Onshore wind project Q318, San Juan County Onshore wind |
1,000 MW | Paused / redesign |
San Juan, NM | West |
Sep 2019 | target 2026 |
Onshore wind project Q319, San Juan County Onshore wind |
1,000 MW | Paused / redesign |
San Juan, NM | West |
Sep 2019 | target 2026 |
Onshore wind project 391 Onshore wind |
750 MW | Paused / redesign |
| West |
Aug 2020 | target 2023 |
Onshore wind project 418, Wheatland County Onshore wind |
750 MW | In study |
Wheatland, MT | West |
Jan 2022 | target 2026 |
Onshore wind project 356, Rosebud County Onshore wind |
750 MW | In study |
Rosebud, MT | West |
Oct 2018 | target 2021 |
Onshore wind project C012, Wheatland County Onshore wind |
750 MW | In study |
Wheatland, MT | West |
Jul 2020 | target 2023 |
Onshore wind project 357, Rosebud County Onshore wind |
750 MW | In study |
Rosebud, MT | West |
Oct 2018 | target 2021 |
Onshore wind project Company MY, Lassen County Onshore wind |
715 MW | Paused / redesign |
Lassen, CA | West |
Mar 2022 | target 2032 |
Onshore wind project 5RSC-2024-17, Kit Carson County Onshore wind |
603 MW | In study |
Kit Carson, CO | West |
Jan 2024 | target 2026 |
Onshore wind project GI-2016-3, Lincoln County Onshore wind |
600 MW | Agreement signed |
Lincoln, CO | West |
Feb 2016 | target 2018 |
Onshore wind project 366, Rosebud County Onshore wind |
600 MW | Paused / redesign |
Rosebud, MT | West |
Sep 2019 | target 2022 |
Onshore wind project C006, Wheatland County Onshore wind |
600 MW | In study |
Wheatland, MT | West |
Feb 2019 | target 2021 |
Onshore wind project 82, Meagher County Onshore wind |
600 MW | Agreement signed |
Meagher, MT | West |
Feb 2019 | |
Onshore wind project G0953, Lincoln County Onshore wind |
600 MW | In study |
Lincoln, WA | West |
Oct 2023 | target 2026 |
Onshore wind project 361, Wheatland County Onshore wind |
600 MW | In study |
Wheatland, MT | West |
Mar 2019 | target 2021 |
Onshore wind project 5RSC-2024-29, Yuma County Onshore wind |
554 MW | In study |
Yuma, CO | West |
Jan 2024 | target 2027 |
Onshore wind project C1-35, Carbon County Onshore wind Β· Lucky Star Wind, LLC |
500 MW | Agreement signed |
Carbon, WY | West |
May 2021 | target 2028 |
Onshore wind project 10-037, Gilliam County Onshore wind |
500 MW | Paused / redesign |
Gilliam, OR | West |
Aug 2010 | target 2015 |
Onshore wind project NC5-008, Mohave County Onshore wind |
500 MW | In study |
Mohave, AZ | West |
May 2021 | target 2025 |
Onshore wind project GI-2016-14, Cheyenne County Onshore wind |
500 MW | Agreement signed |
Cheyenne, CO | West |
Jul 2016 | 2020 |
Onshore wind project G0861, Deschutes County Onshore wind |
500 MW | In study |
Deschutes, OR | West |
Apr 2023 | target 2027 |
Onshore wind project G0619, Wasco County Onshore wind |
500 MW | In study |
Wasco, OR | West |
Apr 2019 | target 2023 |
Onshore wind project G0870, Lake County Onshore wind |
500 MW | In study |
Lake, OR | West |
Jun 2023 | target 2028 |
Onshore wind project 2025-G3 Onshore wind |
500 MW | In study |
| West |
Aug 2025 | target 2028 |
Onshore wind project G0558, Benton County Onshore wind |
500 MW | In study |
Benton, WA | West |
Feb 2017 | target 2019 |
Onshore wind project G0871, Lake County Onshore wind |
500 MW | In study |
Lake, OR | West |
Jun 2023 | target 2028 |
Onshore wind project 5RSC-2024-15, Kiowa County Onshore wind |
500 MW | In study |
Kiowa, CO | West |
Jan 2024 | target 2027 |
Onshore wind project 5RSC-2024-28, Kit Carson County Onshore wind |
500 MW | In study |
Kit Carson, CO | West |
Jan 2024 | target 2025 |
Onshore wind project CSUT-2025-1, Lincoln County Onshore wind |
500 MW | In study |
Lincoln, CO | West |
Mar 2025 | target 2027 |
Onshore wind project 2025-G4 Onshore wind |
500 MW | In study |
| West |
Aug 2025 | target 2028 |
Onshore wind project Q539, Coconino County Onshore wind |
500 MW | In study |
Coconino, AZ | West |
Sep 2023 | target 2027 |
Onshore wind project Q538, Coconino County Onshore wind |
500 MW | In study |
Coconino, AZ | West |
Sep 2023 | target 2027 |
Onshore wind project G0344, Gilliam County Onshore wind |
488 MW | In study |
Gilliam, OR | West |
Sep 2008 | target 2024 |
Onshore wind project Q273, Navajo County Onshore wind |
477 MW | In study |
Navajo, AZ | West |
Mar 2018 | target 2021 |
Onshore wind project 5RSC-2024-16, Cheyenne County Onshore wind |
450 MW | In study |
Cheyenne, CO | West |
Jan 2024 | target 2026 |
Onshore wind project GI-2024-13, Adams County Onshore wind |
423 MW | In study |
Adams, CO | West |
May 2024 | target 2028 |
Onshore wind project GI-2024-12, Adams County Onshore wind |
423 MW | In study |
Adams, CO | West |
May 2024 | target 2028 |
Onshore wind project IA-PNM-2016-02, Torrance Cty County Onshore wind Β· Pacific Wind Development |
402 MW | Agreement signed |
Torrance Cty, NM | West |
May 2016 | target 2020 |
Onshore wind project 09-035, Gilliam County Onshore wind |
401 MW | Paused / redesign |
Gilliam, OR | West |
Jul 2009 | target 2013 |
Onshore wind project T2-057, Carbon County Onshore wind |
400 MW | In study |
Carbon, WY | West |
Sep 2025 | target 2029 |
Onshore wind project GI-2006-1g, Logan County Onshore wind |
400 MW | Agreement signed |
Logan, CO | West |
Jan 2006 | target 2007 |
Onshore wind project GI-2023-14, Morgan County Onshore wind |
400 MW | Paused / redesign |
Morgan, CO | West |
May 2023 | target 2026 |
Onshore wind project 367, Rosebud County Onshore wind |
400 MW | Paused / redesign |
Rosebud, MT | West |
Sep 2019 | target 2022 |
Onshore wind project C2-106, Lincoln County Onshore wind |
400 MW | In study |
Lincoln, WY | West |
May 2022 | target 2025 |
Onshore wind project 2025-G7 Onshore wind |
400 MW | In study |
| West |
Nov 2025 | target 2029 |
Onshore wind project 11-043, Umatilla County Onshore wind |
400 MW | Paused / redesign |
Umatilla, OR | West |
Jun 2011 | target 2014 |
Onshore wind project 10-036, Sherman County Onshore wind |
400 MW | Paused / redesign |
Sherman, OR | West |
Mar 2010 | target 2014 |
Onshore wind project GI-TC-2024-16, Laramie County Onshore wind |
400 MW | Agreement signed |
Laramie, WY | West |
May 2023 | target 2029 |
Onshore wind project PIS089, Lincoln County Onshore wind |
400 MW | In study |
Lincoln, WY | West |
Oct 2024 | target 2028 |