OCTARY USA Β· INTERCONNECTION QUEUES

Onshore wind interconnection queue in West (non-ISO utilities)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown22963.5 GW
Active in queue63.5 GW229 requests
Agreement signed11.8 GW54 requests
Withdrawn1,220219.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

229 requests Β· page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project Q320, San Juan County
Onshore wind
1,500 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Onshore wind project Q318, San Juan County
Onshore wind
1,000 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Onshore wind project Q319, San Juan County
Onshore wind
1,000 MWPaused / redesign San Juan, NMWest Sep 2019target 2026
Onshore wind project 391
Onshore wind
750 MWPaused / redesign West Aug 2020target 2023
Onshore wind project 418, Wheatland County
Onshore wind
750 MWIn study Wheatland, MTWest Jan 2022target 2026
Onshore wind project 356, Rosebud County
Onshore wind
750 MWIn study Rosebud, MTWest Oct 2018target 2021
Onshore wind project C012, Wheatland County
Onshore wind
750 MWIn study Wheatland, MTWest Jul 2020target 2023
Onshore wind project 357, Rosebud County
Onshore wind
750 MWIn study Rosebud, MTWest Oct 2018target 2021
Onshore wind project Company MY, Lassen County
Onshore wind
715 MWPaused / redesign Lassen, CAWest Mar 2022target 2032
Onshore wind project 5RSC-2024-17, Kit Carson County
Onshore wind
603 MWIn study Kit Carson, COWest Jan 2024target 2026
Onshore wind project GI-2016-3, Lincoln County
Onshore wind
600 MWAgreement signed Lincoln, COWest Feb 2016target 2018
Onshore wind project 366, Rosebud County
Onshore wind
600 MWPaused / redesign Rosebud, MTWest Sep 2019target 2022
Onshore wind project C006, Wheatland County
Onshore wind
600 MWIn study Wheatland, MTWest Feb 2019target 2021
Onshore wind project 82, Meagher County
Onshore wind
600 MWAgreement signed Meagher, MTWest Feb 2019
Onshore wind project G0953, Lincoln County
Onshore wind
600 MWIn study Lincoln, WAWest Oct 2023target 2026
Onshore wind project 361, Wheatland County
Onshore wind
600 MWIn study Wheatland, MTWest Mar 2019target 2021
Onshore wind project 5RSC-2024-29, Yuma County
Onshore wind
554 MWIn study Yuma, COWest Jan 2024target 2027
Onshore wind project C1-35, Carbon County
Onshore wind Β· Lucky Star Wind, LLC
500 MWAgreement signed Carbon, WYWest May 2021target 2028
Onshore wind project 10-037, Gilliam County
Onshore wind
500 MWPaused / redesign Gilliam, ORWest Aug 2010target 2015
Onshore wind project NC5-008, Mohave County
Onshore wind
500 MWIn study Mohave, AZWest May 2021target 2025
Onshore wind project GI-2016-14, Cheyenne County
Onshore wind
500 MWAgreement signed Cheyenne, COWest Jul 20162020
Onshore wind project G0861, Deschutes County
Onshore wind
500 MWIn study Deschutes, ORWest Apr 2023target 2027
Onshore wind project G0619, Wasco County
Onshore wind
500 MWIn study Wasco, ORWest Apr 2019target 2023
Onshore wind project G0870, Lake County
Onshore wind
500 MWIn study Lake, ORWest Jun 2023target 2028
Onshore wind project 2025-G3
Onshore wind
500 MWIn study West Aug 2025target 2028
Onshore wind project G0558, Benton County
Onshore wind
500 MWIn study Benton, WAWest Feb 2017target 2019
Onshore wind project G0871, Lake County
Onshore wind
500 MWIn study Lake, ORWest Jun 2023target 2028
Onshore wind project 5RSC-2024-15, Kiowa County
Onshore wind
500 MWIn study Kiowa, COWest Jan 2024target 2027
Onshore wind project 5RSC-2024-28, Kit Carson County
Onshore wind
500 MWIn study Kit Carson, COWest Jan 2024target 2025
Onshore wind project CSUT-2025-1, Lincoln County
Onshore wind
500 MWIn study Lincoln, COWest Mar 2025target 2027
Onshore wind project 2025-G4
Onshore wind
500 MWIn study West Aug 2025target 2028
Onshore wind project Q539, Coconino County
Onshore wind
500 MWIn study Coconino, AZWest Sep 2023target 2027
Onshore wind project Q538, Coconino County
Onshore wind
500 MWIn study Coconino, AZWest Sep 2023target 2027
Onshore wind project G0344, Gilliam County
Onshore wind
488 MWIn study Gilliam, ORWest Sep 2008target 2024
Onshore wind project Q273, Navajo County
Onshore wind
477 MWIn study Navajo, AZWest Mar 2018target 2021
Onshore wind project 5RSC-2024-16, Cheyenne County
Onshore wind
450 MWIn study Cheyenne, COWest Jan 2024target 2026
Onshore wind project GI-2024-13, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Onshore wind project GI-2024-12, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Onshore wind project IA-PNM-2016-02, Torrance Cty County
Onshore wind Β· Pacific Wind Development
402 MWAgreement signed Torrance Cty, NMWest May 2016target 2020
Onshore wind project 09-035, Gilliam County
Onshore wind
401 MWPaused / redesign Gilliam, ORWest Jul 2009target 2013
Onshore wind project T2-057, Carbon County
Onshore wind
400 MWIn study Carbon, WYWest Sep 2025target 2029
Onshore wind project GI-2006-1g, Logan County
Onshore wind
400 MWAgreement signed Logan, COWest Jan 2006target 2007
Onshore wind project GI-2023-14, Morgan County
Onshore wind
400 MWPaused / redesign Morgan, COWest May 2023target 2026
Onshore wind project 367, Rosebud County
Onshore wind
400 MWPaused / redesign Rosebud, MTWest Sep 2019target 2022
Onshore wind project C2-106, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest May 2022target 2025
Onshore wind project 2025-G7
Onshore wind
400 MWIn study West Nov 2025target 2029
Onshore wind project 11-043, Umatilla County
Onshore wind
400 MWPaused / redesign Umatilla, ORWest Jun 2011target 2014
Onshore wind project 10-036, Sherman County
Onshore wind
400 MWPaused / redesign Sherman, ORWest Mar 2010target 2014
Onshore wind project GI-TC-2024-16, Laramie County
Onshore wind
400 MWAgreement signed Laramie, WYWest May 2023target 2029
Onshore wind project PIS089, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest Oct 2024target 2028
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)