United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in West (non-ISO utilities) (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown23746.1 GW
Active in queue45.5 GW192 requests
Agreement signed1,964 MW16 requests
Withdrawn23746.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

237 requests Β· page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project Q2404, Navajo County
Solar + storage
2,519 MWWithdrawn / abandoned Navajo, AZWest Feb 2024target 2028
Solar + storage project Company QS, Mineral County
Solar + storage
1,500 MWWithdrawn / abandoned Mineral, NVWest Mar 2024target 2028
Solar + storage project C4-092, Harney County
Solar + storage
1,280 MWWithdrawn / abandoned Harney, ORWest May 2024target 2031
Solar + storage project C4-093, Klamath County
Solar + storage
1,280 MWWithdrawn / abandoned Klamath, ORWest May 2024target 2031
Solar + storage project Company QV, Washoe County
Solar + storage
1,000 MWWithdrawn / abandoned Washoe, NVWest Mar 2024target 2029
Solar + storage project Q2408, Navajo County
Solar + storage
912 MWWithdrawn / abandoned Navajo, AZWest Feb 2024target 2027
Onshore wind project 169, Cochise County
Onshore wind
900 MWWithdrawn / abandoned Cochise, AZWest Jun 2024target 2028
Other project Q551, Coconino County
Other
700 MWWithdrawn / abandoned Coconino, AZWest Apr 2024target 2028
Solar + storage project C4-026, Harney County
Solar + storage
640 MWWithdrawn / abandoned Harney, ORWest May 2024target 2028
Onshore wind project C4-033, Millard County
Onshore wind
600 MWWithdrawn / abandoned Millard, UTWest May 2024target 2028
Gas project C4-082, Juab County
Gas
550 MWWithdrawn / abandoned Juab, UTWest May 2024target 2028
Battery storage project C4-019, Owyhee County
Battery storage
540 MWWithdrawn / abandoned Owyhee, IDWest May 2024target 2027
Gas project C4-083, San Juan County
Gas
525 MWWithdrawn / abandoned San Juan, UTWest May 2024target 2028
Solar + storage project C4-011, Morrow County
Solar + storage
500 MWWithdrawn / abandoned Morrow, ORWest Apr 2024target 2028
Solar + storage project Company QR, Washoe County
Solar + storage
500 MWWithdrawn / abandoned Washoe, NVWest Mar 2024target 2028
Solar + storage project Company QY, Churchill County
Solar + storage
500 MWWithdrawn / abandoned Churchill, NVWest Mar 2024target 2028
Solar + storage project 171, Pinal County
Solar + storage
500 MWWithdrawn / abandoned Pinal, AZWest Jun 2024target 2028
Solar + storage project C4-028, Blaine County
Solar + storage
500 MWWithdrawn / abandoned Blaine, IDWest May 2024target 2028
Battery storage project C4-022, Salt Lake County
Battery storage
500 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2029
Solar + storage project 166, Graham County
Solar + storage
485 MWWithdrawn / abandoned Graham, AZWest Apr 2024target 2028
Solar project C4-086, Emery County
Solar
450 MWWithdrawn / abandoned Emery, UTWest May 2024target 2029
Solar + storage project Q2416, Maricopa County
Solar + storage
420 MWWithdrawn / abandoned Maricopa, AZWest Feb 2024target 2029
Onshore wind project C4-020, San Juan County
Onshore wind
402 MWWithdrawn / abandoned San Juan, UTWest May 2024target 2028
Solar project 167, Cochise County
Solar
400 MWWithdrawn / abandoned Cochise, AZWest Apr 2024target 2029
Solar + storage project 172, Cochise County
Solar + storage
400 MWWithdrawn / abandoned Cochise, AZWest Jun 2024target 2028
Solar + storage project C4-023, Utah County
Solar + storage
400 MWWithdrawn / abandoned Utah, UTWest May 2024target 2030
Gas project C4-030, Power County
Gas
400 MWWithdrawn / abandoned Power, IDWest May 2024target 2030
Onshore wind project C4-085, Carbon County
Onshore wind
400 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2029
Solar + storage project C4-034, Emery County
Solar + storage
400 MWWithdrawn / abandoned Emery, UTWest May 2024target 2030
Solar + storage project C4-089, Utah County
Solar + storage
400 MWWithdrawn / abandoned Utah, UTWest May 2024target 2027
Solar + storage project C4-042, Carbon County
Solar + storage
330 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2029
Onshore wind project C4-036, Carbon County
Onshore wind
310 MWWithdrawn / abandoned Carbon, WYWest May 2024target 2031
Solar + storage project Q2410, Pinal County
Solar + storage
301 MWWithdrawn / abandoned Pinal, AZWest Feb 2024target 2027
Wind + storage project CLPT G28, Converse County
Wind + storage
300 MWWithdrawn / abandoned Converse, WYWest Jan 2024target 2026
Solar + storage project C4-039, Franklin County
Solar + storage
300 MWWithdrawn / abandoned Franklin, IDWest May 2024target 2028
Onshore wind project 168, Cochise County
Onshore wind
300 MWWithdrawn / abandoned Cochise, AZWest Apr 2024target 2030
Solar + storage project C4-111, Iron County
Solar + storage
300 MWWithdrawn / abandoned Iron, UTWest May 2024target 2029
Solar + storage project C4-043, Sanpete County
Solar + storage
300 MWWithdrawn / abandoned Sanpete, UTWest May 2024target 2029
Onshore wind project C4-018, Bingham County
Onshore wind
300 MWWithdrawn / abandoned Bingham, IDWest May 2024target 2028
Onshore wind project C4-106, Bingham County
Onshore wind
300 MWWithdrawn / abandoned Bingham, IDWest May 2024target 2030
Solar + storage project C4-040, Millard County
Solar + storage
300 MWWithdrawn / abandoned Millard, UTWest May 2024target 2027
Battery storage project Q2411, Pinal County
Battery storage
271 MWWithdrawn / abandoned Pinal, AZWest Feb 2024target 2028
Solar + storage project GI-TC-2024-13, Routt County
Solar + storage
250 MWWithdrawn / abandoned Routt, COWest May 2024target 2027
Other project Q577, San Juan County
Other
250 MWWithdrawn / abandoned San Juan, NMWest May 2024target 2028
Battery storage project C4-048, Salt Lake County
Battery storage
250 MWWithdrawn / abandoned Salt Lake, UTWest May 2024target 2027
Battery storage project C4-017, Jackson County
Battery storage
250 MWWithdrawn / abandoned Jackson, ORWest May 2024target 2028
Solar + storage project C4-114, Iron County
Solar + storage
248 MWWithdrawn / abandoned Iron, UTWest May 2024target 2029
Solar + storage project 24-258, Jefferson County
Solar + storage
225 MWWithdrawn / abandoned Jefferson, ORWest May 2024target 2028
Solar + storage project IA-PNM-2024-03, Otero County
Solar + storage
225 MWWithdrawn / abandoned Otero, NMWest Jun 2024target 2027
Battery storage project Q2401, Maricopa County
Battery storage
204 MWWithdrawn / abandoned Maricopa, AZWest Feb 2024target 2028
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)