SOLAR + STORAGE Β· WESTSolar + storage project Company QY, Churchill County
Solar + storage project Company QY, Churchill County is a 500 MW solar + storage request withdrawn in the West interconnection queue, in Churchill County, Nevada, connecting to NV Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2024 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Company QY
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NV Energy
- Location
- Churchill County, Nevada
- Technology
- Solar: 500 MW Β· Battery
- Total requested
- 500 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 28 March 2024
- Proposed online date
- November 2028
Location
Marker shows the centre of Churchill County; the queue data does not give exact sites.
Other requests in Churchill County
- Solar + storage project Company MI, Churchill CountySolar + storage Β· 700 MW Β· agreement signed
- Solar + storage project Company JK, Churchill CountySolar + storage Β· 500 MW Β· agreement signed
- Solar + storage project Company MH, Churchill CountySolar + storage Β· 300 MW Β· agreement signed
- Solar + storage project Company JE, Churchill CountySolar + storage Β· 125 MW Β· agreement signed
- Geothermal project Company EV, Churchill CountyGeothermal Β· 38.5 MW Β· agreement signed
- Geothermal project Company KZ, Churchill CountyGeothermal Β· 38.5 MW Β· agreement signed
- Geothermal project Company HU, Churchill CountyGeothermal Β· 38.5 MW Β· agreement signed
- Geothermal project 25-00406, Churchill CountyGeothermal Β· 600 MW Β· in study
- Geothermal project 25-00409, Churchill CountyGeothermal Β· 600 MW Β· in study
- Solar + storage project Company QX, Churchill CountySolar + storage Β· 240 MW Β· in study
- Geothermal project 25-00405, Churchill CountyGeothermal Β· 200 MW Β· in study
- Geothermal project 25-00408, Churchill CountyGeothermal Β· 200 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem