United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in West (non-ISO utilities)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project G0757, Columbia County Solar + storage |
3,800 MW | Withdrawn / abandoned |
| Solar + storage project G0759, Sherman County Solar + storage |
3,800 MW | Withdrawn / abandoned |
| Solar + storage project G0754, Marion County Solar + storage |
3,800 MW | Withdrawn / abandoned |
| Solar + storage project G0756, Lake County Solar + storage |
3,800 MW | Withdrawn / abandoned |
| Solar + storage project G0697, Crook County Solar + storage |
3,600 MW | Withdrawn / abandoned |
| Solar + storage project G0696, Crook County Solar + storage |
2,600 MW | Withdrawn / abandoned |
| Solar + storage project Q2507, Pinal County Solar + storage |
2,538 MW | Withdrawn / abandoned |
| Solar + storage project Q2404, Navajo County Solar + storage |
2,519 MW | Withdrawn / abandoned |
| Solar + storage project G0748, Klamath County Solar + storage |
2,378 MW | Withdrawn / abandoned |
| Nuclear project G0869, Benton County Nuclear |
2,200 MW | Withdrawn / abandoned |
| Onshore wind project GI-0612, Hand County Onshore wind |
2,000 MW | Withdrawn / abandoned |
| Solar + storage project Q109, Navajo County Solar + storage |
2,000 MW | Withdrawn / abandoned |
| Solar + storage project Q33, Pinal County Solar + storage |
2,000 MW | Withdrawn / abandoned |
| Solar + storage project G0698, Crook County Solar + storage |
1,800 MW | Withdrawn / abandoned |
| Battery storage project C2-19, Kootenai County Battery storage ยท PacifiCorp |
1,800 MW | Withdrawn / abandoned |
| Battery storage project Q400, Coconino County Battery storage |
1,700 MW | Withdrawn / abandoned |
| Solar + storage project Q469, Pinal County Solar + storage |
1,650 MW | Withdrawn / abandoned |
| Other project 63, Power County Other |
1,577 MW | Withdrawn / abandoned |
| Solar + storage project Company PM, Esmeralda County Solar + storage |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project Q75, Apache County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Solar + storage project Q341, Coconino County Solar + storage |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project 177, Carbon County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Solar + storage project Company QS, Mineral County Solar + storage |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project GI-0611, Hand County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project GI-0609, Buffalo County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Solar + storage project G0852, Wasco County Solar + storage |
1,500 MW | Withdrawn / abandoned |
| 1300MW Sickler-Schultz Gas ยท Calpine Energy Services, L.P. |
1,300 MW | Withdrawn / abandoned |
| Competitive Power Venture Gas ยท Newport Northwest, LLC |
1,300 MW | Withdrawn / abandoned |
| Hydro project Q499, Riverside County Hydro |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project G0966, Umatilla County Solar + storage |
1,300 MW | Withdrawn / abandoned |
| Kootenai Generation Gas |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project G0962, Morrow County Solar + storage |
1,300 MW | Withdrawn / abandoned |
| Grant Generation Gas ยท Grant Generation, LLC |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project G0781, Morrow County Solar + storage |
1,300 MW | Withdrawn / abandoned |
| Grant Generation Gas ยท Grant Generation, LLC |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project G0960, Morrow County Solar + storage |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project G0964, Umatilla County Solar + storage |
1,300 MW | Withdrawn / abandoned |
| Other project Q82, Apache County Other |
1,300 MW | Withdrawn / abandoned |
| Solar + storage project C4-092, Harney County Solar + storage |
1,280 MW | Withdrawn / abandoned |
| Solar + storage project C4-093, Klamath County Solar + storage |
1,280 MW | Withdrawn / abandoned |
| Solar project G0624, Garfield County Solar |
1,250 MW | Withdrawn / abandoned |
| Gas project Q41, Pinal County Gas |
1,213 MW | Withdrawn / abandoned |
| Solar + storage project G0700, Crook County Solar + storage |
1,200 MW | Withdrawn / abandoned |
| Battery storage project G0350, Klickitat County Battery storage |
1,200 MW | Withdrawn / abandoned |
| Other project Q218, San Juan County Other |
1,200 MW | Withdrawn / abandoned |
| Coal project Q25, Navajo County Coal |
1,200 MW | Withdrawn / abandoned |
| Peoples Energy Resources Gas ยท Peoples Energy Resources Corporation |
1,200 MW | Withdrawn / abandoned |
| Battery storage project G0556, Klickitat County Battery storage |
1,200 MW | Withdrawn / abandoned |
| Battery storage project G0351, Klickitat County Battery storage |
1,200 MW | Withdrawn / abandoned |
| Solar + storage project G0701, Crook County Solar + storage |
1,200 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 ยท 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 ยท 638.1 GW
- MISO (Midcontinent)3,261 ยท 621.9 GW
- CAISO (California)2,186 ยท 619.9 GW
- Southeast (non-ISO utilities)2,738 ยท 603.3 GW
- SPP (Southwest Power Pool)1,846 ยท 382.9 GW
- NYISO (New York)1,531 ยท 324.1 GW
- ERCOT (Texas)1,158 ยท 262.0 GW
- ISO-NE (New England)982 ยท 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)