United States βΊ Grid βΊ Interconnection queues βΊ Idaho
OTHER Β· WESTOther project 63, Power County
Other project 63, Power County is a 1,577 MW other request withdrawn in the West interconnection queue, in Power County, Idaho, connecting to Idaho Power Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2001 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 63
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Idaho Power Company
- Connection point (POI)
- undefined
- Location
- Power County, Idaho
- Technology
- Other: 1,577 MW
- Total requested
- 1,577 MW
- Queue status
- Withdrawn
- Entered queue
- 12 September 2001
- Proposed online date
- May 2004
Location
Marker shows the centre of Power County; the queue data does not give exact sites.
Other requests in Power County
- Solar + storage project C2-45, Power CountySolar + storage Β· 600 MW Β· agreement signed
- Solar + storage project 573, Power CountySolar + storage Β· 300 MW Β· agreement signed
- Gas project T2-040, Power CountyGas Β· 400 MW Β· in study
- Onshore wind project 763, Power CountyOnshore wind Β· 300 MW Β· in study
- Solar + storage project 662, Power CountySolar + storage Β· 1,000 MW Β· suspended
- Battery storage project 641, Power CountyBattery storage Β· 200 MW Β· suspended
- Hydro project 795, Power CountyHydro Β· 118 MW Β· built
- Onshore wind project 293, Power CountyOnshore wind Β· 80.0 MW Β· built
- Onshore wind project 323-A, Power CountyOnshore wind Β· 21.6 MW Β· built
- Onshore wind project 323-B, Power CountyOnshore wind Β· 21.6 MW Β· built
- Solar project 431, Power CountySolar Β· 20.0 MW Β· built
- Solar project 433, Power CountySolar Β· 20.0 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem