πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

SOLAR + STORAGE Β· WEST

Solar + storage project G0960, Morrow County

Solar + storage project G0960, Morrow County is a 1,300 MW solar + storage request withdrawn in the West interconnection queue, in Morrow County, Oregon.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0960
Grid region
West (non-ISO utilities)
Connection point (POI)
Longhorn Substation at 230 kV
Location
Morrow County, Oregon
Technology
Solar: 650 MW Β· Battery: 650 MW
Total requested
1,300 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
11 October 2023
Proposed online date
December 2026

Location

Marker shows the centre of Morrow County; the queue data does not give exact sites.

Power plants in Oregon Β· Transmission lines in Oregon

Other requests in Morrow County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem