πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Wyoming

ONSHORE WIND Β· WEST

Onshore wind project 177, Carbon County

Onshore wind project 177, Carbon County is a 1,500 MW onshore wind request withdrawn in the West interconnection queue, in Carbon County, Wyoming, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2007 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
177
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Line near proposed Aeolus substation.
Location
Carbon County, Wyoming
Technology
Wind: 1,500 MW
Total requested
1,500 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
27 December 2007
Proposed online date
October 2014

Location

Marker shows the centre of Carbon County; the queue data does not give exact sites.

Power plants in Wyoming Β· Transmission lines in Wyoming

Other requests in Carbon County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem