United States β€Ί Grid β€Ί Interconnection queues β€Ί Oregon

SOLAR + STORAGE Β· WEST

Solar + storage project G0781, Morrow County

Solar + storage project G0781, Morrow County is a 1,300 MW solar + storage request withdrawn in the West interconnection queue, in Morrow County, Oregon.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2022 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G0781
Grid region
West (non-ISO utilities)
Connection point (POI)
Roughly 2-15 miles West of BPA Longhorn 230kV substation
Location
Morrow County, Oregon
Technology
Solar: 650 MW Β· Battery: 650 MW
Total requested
1,300 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
18 August 2022
Proposed online date
December 2028

Location

Marker shows the centre of Morrow County; the queue data does not give exact sites.

Power plants in Oregon Β· Transmission lines in Oregon

Other requests in Morrow County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem