Interconnection queue in Colorado, West

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown20943.2 GW
Active in queue43.2 GW209 requests
Agreement signed11.0 GW60 requests
Withdrawn36173.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

209 requests Β· page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GI-2025-04, Kiowa County
Solar + storage
800 MWIn study Kiowa, COWest Apr 2025target 2032
Solar + storage project GI-2025-06, Arapahoe County
Solar + storage
750 MWIn study Arapahoe, COWest Apr 2025target 2029
Coal project GI-2003-3, Pueblo County
Coal
750 MWAgreement signed Pueblo, COWest Nov 2003target 2009
Gas project GI-2011-4, Denver County
Gas
687 MWAgreement signed Denver, COWest Apr 2011target 2015
Onshore wind project 5RSC-2024-17, Kit Carson County
Onshore wind
603 MWIn study Kit Carson, COWest Jan 2024target 2026
Onshore wind project GI-2016-3, Lincoln County
Onshore wind
600 MWAgreement signed Lincoln, COWest Feb 2016target 2018
Onshore wind project 5RSC-2024-29, Yuma County
Onshore wind
554 MWIn study Yuma, COWest Jan 2024target 2027
Solar project 5RSC-2024-22, Crowley County
Solar
500 MWIn study Crowley, COWest Jan 2024target 2027
Solar + storage project GI-2024-06, Morgan County
Solar + storage
500 MWIn study Morgan, COWest May 2024target 2027
Onshore wind project GI-2016-14, Cheyenne County
Onshore wind
500 MWAgreement signed Cheyenne, COWest Jul 20162020
Onshore wind project 5RSC-2024-15, Kiowa County
Onshore wind
500 MWIn study Kiowa, COWest Jan 2024target 2027
Onshore wind project 5RSC-2024-28, Kit Carson County
Onshore wind
500 MWIn study Kit Carson, COWest Jan 2024target 2025
Onshore wind project CSUT-2025-1, Lincoln County
Onshore wind
500 MWIn study Lincoln, COWest Mar 2025target 2027
Gas project GI-2006-1e, El Paso County
Gas
483 MWAgreement signed El Paso, COWest Jan 2006target 2007
Onshore wind project 5RSC-2024-16, Cheyenne County
Onshore wind
450 MWIn study Cheyenne, COWest Jan 2024target 2026
Onshore wind project GI-2024-13, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Onshore wind project GI-2024-12, Adams County
Onshore wind
423 MWIn study Adams, COWest May 2024target 2028
Gas project CSUT-2025-7, El Paso County
Gas
412 MWIn study El Paso, COWest Mar 2025target 2028
Onshore wind project GI-2006-1g, Logan County
Onshore wind
400 MWAgreement signed Logan, COWest Jan 2006target 2007
Onshore wind project GI-2023-14, Morgan County
Onshore wind
400 MWPaused / redesign Morgan, COWest May 2023target 2026
Solar + storage project GI-2024-05, Pueblo County
Solar + storage
400 MWIn study Pueblo, COWest Apr 2024target 2028
Gas project 5RSC-2024-02, Weld County
Gas
400 MWIn study Weld, COWest Jan 2024target 2027
Solar project GI-2025-09, Cheyenne County
Solar
400 MWIn study Cheyenne, COWest Apr 2025target 2029
Solar project 5RSC-2024-21, Crowley County
Solar
400 MWIn study Crowley, COWest Jan 2024target 2029
Solar + storage project GI-2025-08, El Paso County
Solar + storage
400 MWIn study El Paso, COWest Apr 2025target 2029
Solar + storage project GI-TC-2024-30, Morgan County
Solar + storage
400 MWAgreement signed Morgan, COWest May 2024target 2028
Solar + storage project GI-TC-2024-31, Elbert County
Solar + storage
398 MWIn study Elbert, COWest May 2024target 2028
Solar + storage project GI-DISIS-2022-13, Prowers County
Solar + storage
398 MWAgreement signed Prowers, COWest May 2022target 2029
Gas project GI-2007-11, Weld County
Gas
380 MWAgreement signed Weld, COWest Oct 2007target 2009
Solar + storage project GI-2025-07, Morgan County
Solar + storage
360 MWIn study Morgan, COWest Apr 2025target 2029
Solar + storage project GI-2025-12, Adams County
Solar + storage
355 MWIn study Adams, COWest May 2025target 2029
Onshore wind project GI-TC-2024-25, Weld County
Onshore wind
350 MWIn study Weld, COWest May 2024target 2028
Solar + storage project GI-2025-03, Kiowa County
Solar + storage
325 MWIn study Kiowa, COWest Apr 2025target 2031
Solar + storage project GI-CS-2025-21, Pueblo County
Solar + storage
325 MWIn study Pueblo, COWest Sep 2025target 2030
Solar + storage project TI-19-0227, La Plata County
Solar + storage
310 MWPaused / redesign La Plata, COWest Mar 2021target 2027
Onshore wind project GI-2006-1i, Weld County
Onshore wind
300 MWAgreement signed Weld, COWest Jan 2006target 2007
Solar project GI-CS-2025-05, Weld County
Solar
300 MWIn study Weld, COWest Sep 2025target 2029
Onshore wind project GI-2016-4, Lincoln County
Onshore wind
300 MWAgreement signed Lincoln, COWest Feb 2016target 2018
Solar + storage project 5RSC-2024-06, Pueblo County
Solar + storage
300 MWIn study Pueblo, COWest Jan 2024target 2028
Solar + storage project GI-2025-02, Cheyenne County
Solar + storage
300 MWIn study Cheyenne, COWest Apr 2025target 2030
Other project GI-CS-2025-29, Yuma County
Other
300 MWIn study Yuma, COWest Oct 2025target 2031
Solar + storage project GI-DISIS-2021-11, Las Animas County
Solar + storage
300 MWPaused / redesign Las Animas, COWest May 2021target 2026
Solar + storage project GI-2025-01, Morgan County
Solar + storage
300 MWIn study Morgan, COWest Apr 2025target 2030
Solar + storage project GI-CS-2025-03, Kit Carson County
Solar + storage
300 MWIn study Kit Carson, COWest Sep 2025target 2028
Solar + storage project GI-DISIS-2022-28, Kit Carson County
Solar + storage
299 MWPaused / redesign Kit Carson, COWest May 2022target 2029
Solar + storage project GI-DISIS-2022-45, Pueblo County
Solar + storage
299 MWPaused / redesign Pueblo, COWest May 2022target 2028
Solar + storage project GI-DISIS-2022-44, Moffat County
Solar + storage
299 MWPaused / redesign Moffat, COWest May 2022target 2030
Solar + storage project GI-DISIS-2022-02, Weld County
Solar + storage
299 MWAgreement signed Weld, COWest May 2022target 2030
Solar + storage project GI-DISIS-2022-07, Weld County
Solar + storage
299 MWAgreement signed Weld, COWest May 2022target 2029
Onshore wind project 5RSC-2024-18, Prowers County
Onshore wind
293 MWIn study Prowers, COWest Jan 2024target 2029
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)