United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Southeast (non-ISO utilities) (2016 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project 24745, Cumberland County Gas Β· Duke Energy Progress - Cumberland South - 500 kV |
1,235 MW | Withdrawn / abandoned |
| Gas project 24735, Cumberland County Gas Β· Duke Energy Progress, LLC |
1,235 MW | Withdrawn / abandoned |
| Gas project 16 Gas |
1,190 MW | Withdrawn / abandoned |
| Gas project 143, Volusia County Gas Β· Masked |
1,180 MW | Withdrawn / abandoned |
| Gas project 157, Volusia County Gas Β· Masked |
1,174 MW | Withdrawn / abandoned |
| Gas project 19 Gas |
655 MW | Withdrawn / abandoned |
| Gas project 156, Volusia County Gas Β· Masked |
655 MW | Withdrawn / abandoned |
| Solar project 142, Osceola County Solar Β· Masked |
617 MW | Withdrawn / abandoned |
| Gas project 13 Gas |
609 MW | Withdrawn / abandoned |
| Other project 144, Sumter County Other Β· Masked |
560 MW | Withdrawn / abandoned |
| Solar project 298, Haywood County Solar |
400 MW | Withdrawn / abandoned |
| Solar project IC-444, Jackson County Solar |
295 MW | Withdrawn / abandoned |
| Solar project IC-539, Coffee County Solar |
250 MW | Withdrawn / abandoned |
| Solar project IC-544, Laurens County Solar |
240 MW | Withdrawn / abandoned |
| Solar project IC-537, Jeff Davis County Solar |
215 MW | Withdrawn / abandoned |
| Solar project IC-442, Jackson County Solar |
213 MW | Withdrawn / abandoned |
| Onshore wind project GI-58, Kingfisher County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project 293, Panola County Solar |
200 MW | Withdrawn / abandoned |
| Solar project IC-496, Pulaski County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project GI-59, Osage County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project IC-542, Toombs County Solar |
200 MW | Withdrawn / abandoned |
| Solar project IC-490, Burke County Solar |
200 MW | Withdrawn / abandoned |
| Solar project IC-472, Dougherty County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project GI-57, Osage County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project IC-540, Dooly County Solar |
180 MW | Withdrawn / abandoned |
| Solar project IC-476, Turner County Solar |
170 MW | Withdrawn / abandoned |
| Solar project IC-457, Tift County Solar |
165 MW | Withdrawn / abandoned |
| Solar project IC-445, Sumter County Solar |
152 MW | Withdrawn / abandoned |
| Solar project IC-447, Sumter County Solar |
152 MW | Withdrawn / abandoned |
| Solar project IC-446, Sumter County Solar |
152 MW | Withdrawn / abandoned |
| Solar project 302, Jackson County Solar |
150 MW | Withdrawn / abandoned |
| Onshore wind project GI-52, Osage County Onshore wind |
144 MW | Withdrawn / abandoned |
| Solar project IC-550, Coffee County Solar |
143 MW | Withdrawn / abandoned |
| Solar project IC-465, Jefferson County Solar |
128 MW | Withdrawn / abandoned |
| Solar project IC-562, Early County Solar |
125 MW | Withdrawn / abandoned |
| Solar project IC-458, Clay County Solar |
122 MW | Withdrawn / abandoned |
| Solar project IC-508, Toombs County Solar |
120 MW | Withdrawn / abandoned |
| Solar project IC-467, Decatur County Solar |
118 MW | Withdrawn / abandoned |
| Solar project IC-489, Burke County Solar |
100 MW | Withdrawn / abandoned |
| Solar project IC-435, Taylor County Solar |
100 MW | Withdrawn / abandoned |
| Solar project IC-553, Appling County Solar |
100 MW | Withdrawn / abandoned |
| Solar project IC-436, Decatur County Solar |
100 MW | Withdrawn / abandoned |
| Solar project IC-461, Dooly County Solar |
100 MW | Withdrawn / abandoned |
| Solar project IC-497, Pulaski County Solar |
100 MW | Withdrawn / abandoned |
| Solar project 8277, Lee County Solar Β· Masked |
100 MW | Withdrawn / abandoned |
| Solar + storage project IC-448, Randolph County Solar + storage |
100 MW | Withdrawn / abandoned |
| Solar project 39370, Sumter County Solar Β· Duke Energy Renewables Solar LLC |
100 MW | Withdrawn / abandoned |
| Solar project 296, Jackson County Solar |
100 MW | Withdrawn / abandoned |
| Solar project IC-437, Decatur County Solar |
100 MW | Withdrawn / abandoned |
| Solar project IC-439, Decatur County Solar |
100 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)185 Β· 25.4 GW
- Southeast (non-ISO utilities)212 Β· 25.1 GW
- PJM (Mid-Atlantic, Midwest)250 Β· 23.8 GW
- West (non-ISO utilities)255 Β· 23.7 GW
- CAISO (California)96 Β· 19.6 GW
- SPP (Southwest Power Pool)110 Β· 19.5 GW
- ERCOT (Texas)39 Β· 7,318 MW
- ISO-NE (New England)22 Β· 4,400 MW
- NYISO (New York)25 Β· 2,046 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)