SOLAR Β· SOUTHEAST

Solar project IC-461, Dooly County

Solar project IC-461, Dooly County is a 100 MW solar request withdrawn in the Southeast interconnection queue, in Dooly County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedNov 2021 (project stopped here)
  3. ConsentedOct 2018 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-461
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
North Americus - Pitts 115 kV Line
Location
Dooly County, Georgia
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
18 May 2016
Agreement signed
15 October 2018
Withdrawn
November 2021

Location

Marker shows the centre of Dooly County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Dooly County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem