United States βΊ Grid βΊ Interconnection queues βΊ Georgia
SOLAR Β· SOUTHEASTSolar project IC-282, Dooly County
Solar project IC-282, Dooly County is a 20.0 MW solar request withdrawn in the Southeast interconnection queue, in Dooly County, Georgia, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2013 (completed)
- Withdrawn / abandonedDec 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-282
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- North Americus - Pitts 115 kV Line
- Location
- Dooly County, Georgia
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 5 March 2013
- Withdrawn
- December 2013
Location
Marker shows the centre of Dooly County; the queue data does not give exact sites.
Other requests in Dooly County
- Solar project IC-540, Dooly CountySolar Β· 180 MW Β· withdrawn
- Solar project IC-461, Dooly CountySolar Β· 100 MW Β· withdrawn
- Solar project IC-283, Dooly CountySolar Β· 20.0 MW Β· withdrawn
- Solar project IC-478, Dooly CountySolar Β· 20.0 MW Β· withdrawn
- Solar project IC-275, Dooly CountySolar Β· 20.0 MW Β· withdrawn
- Solar project IC-263, Dooly CountySolar Β· 20.0 MW Β· withdrawn
- Solar project IC-477, Dooly CountySolar Β· 20.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem