Interconnection queue in Georgia, Southeast

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown20446.5 GW
Active in queue46.5 GW204 requests
Agreement signed16.6 GW57 requests
Withdrawn510106.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

204 requests Β· page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Smarr CC
Gas
2,000 MWIn study Monroe, GASoutheast Aug 2024target 2028
Solar + storage project IC-942, Glynn County
Solar + storage
1,200 MWPaused / redesign Glynn, GASoutheast Mar 2021target 2025
Gas project IC-1254b, Heard County
Gas
1,003 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Gas project IC-1254a, Heard County
Gas
1,003 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Flint River 780 MW Unit
Gas
780 MWIn study Mitchell, GASoutheast Oct 2024target 2029
Flint River 2 780 MW Unit
Gas
780 MWIn study Mitchell, GASoutheast Mar 2025target 2029
Gas project 25-IC-1330, Hancock County
Gas
759 MWIn study Hancock, GASoutheast Apr 2025target 2030
Gas project 25-IC-1329, Putnam County
Gas
759 MWIn study Putnam, GASoutheast Apr 2025target 2030
Gas project 25-IC-1327, Coweta County
Gas
759 MWIn study Coweta, GASoutheast Apr 2025target 2030
Gas project IC-1255, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2028
Gas project IC-1257, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2029
Gas project IC-1256, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2029
Gas project IC-1260, Effingham County
Gas
722 MWIn study Effingham, GASoutheast Mar 2024target 2031
Gas project IC-1264, Heard County
Gas
722 MWAgreement signed Heard, GASoutheast Mar 2024target 2029
Gas project IC-1258, Bartow County
Gas
722 MWAgreement signed Bartow, GASoutheast Mar 2024target 2029
Gas project IC-1263, Heard County
Gas
722 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Gas project IC-1259, Effingham County
Gas
722 MWAgreement signed Effingham, GASoutheast Mar 2024target 2029
Solar project IC-652, Sumter County
Solar
615 MWAgreement signed Sumter, GASoutheast Sep 2017target 2023
Battery storage project IC-974, Fulton County
Battery storage
600 MWPaused / redesign Fulton, GASoutheast Jul 2021target 2025
Battery storage project 25-IC-1374, Hancock County
Battery storage
600 MWIn study Hancock, GASoutheast Apr 2025target 2029
Battery storage project IC-1247, Heard County
Battery storage
500 MWAgreement signed Heard, GASoutheast Mar 2024target 2028
Solar project IC-1147, Monroe County
Solar
500 MWPaused / redesign Monroe, GASoutheast Jun 2023target 2030
Battery storage project IC-1170, Douglas County
Battery storage
500 MWPaused / redesign Douglas, GASoutheast Aug 2023target 2030
Battery storage project 25-IC-1311, Mcduffie County
Battery storage
500 MWIn study Mcduffie, GASoutheast Apr 2025target 2028
Pepper Hammock 500 Solar
Solar
500 MWIn study Glynn, GASoutheast Jul 2022target 2024
Solar project IC-1084, Coweta County
Solar
470 MWPaused / redesign Coweta, GASoutheast Oct 2022target 2027
Battery storage project 25-IC-1385, Hancock County
Battery storage
450 MWIn study Hancock, GASoutheast Apr 2025target 2030
Gas project IC-1166, Coweta County
Gas
411 MWAgreement signed Coweta, GASoutheast Aug 2023target 2025
Gas project IC-1168, Coweta County
Gas
411 MWAgreement signed Coweta, GASoutheast Aug 2023target 2025
Gas project IC-1167, Coweta County
Gas
411 MWAgreement signed Coweta, GASoutheast Aug 2023target 2025
Battery storage project 25-IC-1375, Jackson County
Battery storage
325 MWIn study Jackson, GASoutheast Apr 2025target 2031
TOCE GA Solar 4
Solar + storage
325 MWIn study Jefferson, GASoutheast Jan 2024target 2027
Battery storage project IC-1279, Coweta County
Battery storage
320 MWAgreement signed Coweta, GASoutheast Apr 2024target 2028
Battery storage project IC-1271, Cherokee County
Battery storage
265 MWAgreement signed Cherokee, GASoutheast Mar 2024target 2026
Battery storage project IC-906, Cherokee County
Battery storage
265 MWAgreement signed Cherokee, GASoutheast Oct 2020target 2026
Solar project IC-789, Decatur County
Solar
260 MWAgreement signed Decatur, GASoutheast Apr 2019target 2028
Solar project IC-774, Mitchell County
Solar
260 MWAgreement signed Mitchell, GASoutheast Feb 2019target 2022
Battery storage project IC-1144, Bartow County
Battery storage
260 MWPaused / redesign Bartow, GASoutheast Jun 2023target 2028
Battery storage project 25-IC-1312, Coweta County
Battery storage
250 MWIn study Coweta, GASoutheast Apr 2025target 2028
Solar + storage project IC-932, Glynn County
Solar + storage
250 MWPaused / redesign Glynn, GASoutheast Dec 2020target 2024
Solar project IC-950, Mcduffie County
Solar
250 MWAgreement signed Mcduffie, GASoutheast Apr 2021target 2024
Rock House Solar
Solar + storage
250 MWIn study Mcduffie, GASoutheast Jan 2022target 2025
Solar + storage project IC-933, Glynn County
Solar + storage
250 MWPaused / redesign Glynn, GASoutheast Dec 2020target 2024
Battery storage project 25-IC-1313, Bartow County
Battery storage
250 MWIn study Bartow, GASoutheast Apr 2025target 2028
Solar project IC-695, Sumter County
Solar
250 MWAgreement signed Sumter, GASoutheast May 2018target 2023
Battery storage project IC-1223, Hall County
Battery storage
250 MWAgreement signed Hall, GASoutheast Dec 2023target 2028
Solar project 25-IC-1326, Jasper County
Solar
250 MWIn study Jasper, GASoutheast Apr 2025target 2030
Talbot U7
Gas
250 MWIn study Talbot, GASoutheast Aug 2024target 2029
Battery storage project IC-1222, Bartow County
Battery storage
250 MWAgreement signed Bartow, GASoutheast Dec 2023target 2027
Solar project IC-1149, Mitchell County
Solar
250 MWPaused / redesign Mitchell, GASoutheast Jul 2023target 2028
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)