United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in PJM (Mid-Atlantic, Midwest)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project AE1-222, Grundy County Gas |
2,563 MW | Withdrawn / abandoned |
| Coal project R67, Beaver County Coal |
2,510 MW | Withdrawn / abandoned |
| Onshore wind project T32, Mcpherson County Onshore wind |
2,500 MW | Withdrawn / abandoned |
| Gas project AH1-675, Columbia County Gas ยท Invitium Energy, LLC |
2,175 MW | Withdrawn / abandoned |
| Coal project R68, Jefferson County Coal |
1,940 MW | Withdrawn / abandoned |
| Coal project I07, Jefferson County Coal |
1,860 MW | Withdrawn / abandoned |
| Gas project L01, Charles County Gas |
1,800 MW | Withdrawn / abandoned |
| Gas project M01, Charles County Gas |
1,800 MW | Withdrawn / abandoned |
| Gas project K08, Charles County Gas |
1,800 MW | Withdrawn / abandoned |
| Hatfield Ferry, Units 1, 2, and 3 Coal |
1,710 MW | Withdrawn / abandoned |
| Gas project AH1-674, Beaver County Gas ยท Shippingport Power Station, LLC |
1,700 MW | Withdrawn / abandoned |
| Nuclear project V2-042, Calvert County Nuclear |
1,640 MW | Withdrawn / abandoned |
| Nuclear project Q77, Calvert County Nuclear |
1,640 MW | Withdrawn / abandoned |
| Calvert Cliffs Nuclear Power Plant Unit 3 Nuclear |
1,640 MW | Withdrawn / abandoned |
| Onshore wind project AH2-196, Monmouth County Onshore wind |
1,600 MW | Withdrawn / abandoned |
| Chickahominy Power Gas |
1,600 MW | Withdrawn / abandoned |
| Offshore wind project AI1-046, Monmouth County Offshore wind |
1,600 MW | Withdrawn / abandoned |
| Gas project E17_W26 Gas |
1,595 MW | Withdrawn / abandoned |
| North Anna Power Station Unit 3 Nuclear |
1,594 MW | Withdrawn / abandoned |
| Gas project X2-082, Chesterfield County Gas |
1,575 MW | Withdrawn / abandoned |
| Gas project Y2-097, Brunswick County Gas |
1,551 MW | Withdrawn / abandoned |
| Onshore wind project T35, Lamoure County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project T93, Pocahontas County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project T92, Pocahontas County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project T34, Mcpherson County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Onshore wind project X1-020, Cass County Onshore wind |
1,500 MW | Withdrawn / abandoned |
| Offshore wind project AH2-240, Monmouth County Offshore wind |
1,493 MW | Withdrawn / abandoned |
| Gas project AH1-690, Lucas County Gas ยท CPV Oregon, LLC |
1,475 MW | Withdrawn / abandoned |
| Gas project AB1-003, Indiana County Gas |
1,474 MW | Withdrawn / abandoned |
| Gas project AH1-689, Columbia County Gas ยท Invitium Energy, LLC |
1,450 MW | Withdrawn / abandoned |
| Gas project AH1-688, Columbia County Gas ยท Invitium Energy, LLC |
1,450 MW | Withdrawn / abandoned |
| Offshore wind project AH1-384, Sussex County Offshore wind |
1,410 MW | Withdrawn / abandoned |
| Onshore wind project AH2-285, Middlesex County Onshore wind |
1,400 MW | Withdrawn / abandoned |
| Gas project AA2-142, Somerset County Gas |
1,377 MW | Withdrawn / abandoned |
| Gas project AE2-167, Doddridge County Gas |
1,335 MW | Withdrawn / abandoned |
| Gas project U2-098, Middlesex County Gas |
1,320 MW | Withdrawn / abandoned |
| Larrabee 230 kV IV Offshore wind ยท Atlantic Shores Offshore Wind Project 2, LLC |
1,300 MW | Withdrawn / abandoned |
| Coal project S12, Adams County Coal |
1,300 MW | Withdrawn / abandoned |
| Offshore wind project AG2-055, Middlesex County Offshore wind |
1,300 MW | Withdrawn / abandoned |
| Gas project AC1-153, Grundy County Gas |
1,300 MW | Withdrawn / abandoned |
| Gas project AH1-676, Orange County Gas ยท Virginia Electric and Power Company |
1,295 MW | Withdrawn / abandoned |
| Gas project AC1-096, Pickaway County Gas |
1,277 MW | Withdrawn / abandoned |
| Gas project A40, Dauphin County Gas |
1,271 MW | Withdrawn / abandoned |
| Gas project AD1-090, Washington County Gas |
1,260 MW | Withdrawn / abandoned |
| Gas project AC1-067, Cook County Gas |
1,254 MW | Withdrawn / abandoned |
| Gas project S18, Charles County Gas |
1,250 MW | Withdrawn / abandoned |
| Coal project Y2-095, Randolph County Coal |
1,211 MW | Withdrawn / abandoned |
| Solar project AF1-236, Tyrrell County Solar |
1,210 MW | Withdrawn / abandoned |
| Offshore wind project AE2-251, Monmouth County Offshore wind |
1,200 MW | Withdrawn / abandoned |
| Coal project N43, Lewis County Coal |
1,200 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)5,277 ยท 949.5 GW
- PJM (Mid-Atlantic, Midwest)5,226 ยท 638.1 GW
- MISO (Midcontinent)3,261 ยท 621.9 GW
- CAISO (California)2,186 ยท 619.9 GW
- Southeast (non-ISO utilities)2,738 ยท 603.3 GW
- SPP (Southwest Power Pool)1,846 ยท 382.9 GW
- NYISO (New York)1,531 ยท 324.1 GW
- ERCOT (Texas)1,158 ยท 262.0 GW
- ISO-NE (New England)982 ยท 118.1 GW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)