GAS Β· PJMGas project E17_W26
Gas project E17_W26 is a 1,595 MW gas request withdrawn in the PJM interconnection queue, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2000 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- E17_W26
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Taylorstown 500 kV
- Location
- Pennsylvania
- Technology
- Gas: 1,595 MW
- Total requested
- 1,595 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 14 November 2000
- Proposed online date
- July 2005
Location
No county location in the queue data.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem