United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

GAS Β· PJM

Gas project E17_W26

Gas project E17_W26 is a 1,595 MW gas request withdrawn in the PJM interconnection queue, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2000 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
E17_W26
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Taylorstown 500 kV
Location
Pennsylvania
Technology
Gas: 1,595 MW
Total requested
1,595 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Withdrawn
Entered queue
14 November 2000
Proposed online date
July 2005

Location

No county location in the queue data.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania