πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in PJM (Mid-Atlantic, Midwest) (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown753,202 MW
Active in queue19.2 GW183 requests
Agreement signed11.3 GW123 requests
Withdrawn40938.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

75 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Fox Squirrel Solar
Solar
577 MWOperating Madison, OHPJM Feb 20192024
Union Solar
Solar
325 MWOperating Union, OHPJM Sep 20192024
Mammoth North Solar Project
Solar
300 MWOperating Starke, INPJM Sep 20192024
Bellflower Solar 1
Solar
153 MWOperating Henry, INPJM Mar 20192022
Powell Creek Solar
Solar
150 MWOperating Putnam, OHPJM Feb 20192025
Honeysuckle Solar Project
Solar
150 MWOperating St. Joseph, INPJM Sep 20192025
Wheatsborough Solar
Solar
125 MWOperating Erie, OHPJM Mar 20192025
CPV Maple Hill Solar
Solar
100 MWOperating Cambria, PAPJM Mar 20192023
Clearview Solar I
Solar
99.0 MWOperating Champaign, OHPJM Mar 20192025
Blake Solar
Solar
80.0 MWOperating Jefferson, WVPJM Oct 20192024
Greensville Power Station
Gas
75.0 MWOperating Greensville, VAPJM Mar 20192023
Bartonsville Energy Facility
Solar
70.0 MWOperating Frederick, VAPJM Mar 20192024
Arche Energy Project
Solar
67.0 MWOperating Fulton, OHPJM Mar 20192024
Northumberland Solar
Solar
65.0 MWOperating Northumberland, PAPJM Jan 20192025
High Point II Solar
Solar
50.0 MWOperating Stephenson, ILPJM Jan 20192023
Turkey Creek Solar
Solar
50.0 MWOperating Garrard, KYPJM Mar 20192022
Oak Trail Solar
Solar
50.0 MWOperating Currituck, NCPJM Mar 20192023
Montpelier Solar
Solar
49.0 MWOperating Williams, OHPJM Mar 20192025
Clearview Solar I
Solar
45.0 MWOperating Champaign, OHPJM Aug 20192025
Arche Energy Project
Solar
40.0 MWOperating Fulton, OHPJM Aug 20192024
Glover Creek Solar
Solar
35.0 MWOperating Metcalfe, KYPJM Feb 20192024
Yankee 1-7
Gas
23.5 MWOperating Montgomery, OHPJM Mar 20192022
CL-Viaduct
Solar
20.0 MWOperating Clearfield, PAPJM Mar 20192023
Cottontail Solar 4 aka East Chilli Solar
Solar
20.0 MWOperating Northumberland, PAPJM Feb 20192024
Cottontail Solar 5 aka Walker Solar
Solar
20.0 MWOperating Juniata, PAPJM Feb 20192023
Watlington Solar
Solar
20.0 MWOperating Halifax, VAPJM Aug 20192023
Penn Solar (Cottontail 6)
Solar
20.0 MWOperating Snyder, PAPJM Mar 20192024
Philipsburg-Clarence 34.5 kV
Solar
20.0 MWOperating Clearfield, PAPJM Mar 20192023
Blairs Valley
Solar
20.0 MWOperating Franklin, PAPJM Feb 20192025
Viridity Energy Solutions Montague Storage
Battery storage
20.0 MWOperating Sussex, NJPJM Apr 20192024
Erie Solar
Solar
20.0 MWOperating Erie, PAPJM Apr 20192025
Glover Creek Solar
Solar
20.0 MWOperating Metcalfe, KYPJM Sep 20192024
Pleasant Hill Solar
Solar
20.0 MWOperating City Of Suffolk, VAPJM Dec 20192023
Nickel Solar
Solar
19.9 MWOperating Warren, OHPJM Oct 20192024
Jade Meadow
Solar
19.8 MWOperating Allegany, MDPJM Apr 20192024
BE-PINE 2 Dam Road
Solar
17.1 MWOperating Beaver, PAPJM Mar 20192023
BE-PINE 1 Cain Road
Solar
17.1 MWOperating Beaver, PAPJM Mar 20192023
Stratford Solar Center
Solar
15.0 MWOperating City Of Suffolk, VAPJM May 20192023
Warren County Power Station
Gas
15.0 MWOperating Warren, VAPJM Mar 20192020
Fairview Farms I
Solar
15.0 MWOperating Harford, MDPJM Sep 20192025
Fairview Farms II
Solar
15.0 MWOperating Harford, MDPJM Sep 20192025
Listonburg Solar
Solar
15.0 MWOperating Somerset, PAPJM Jun 20192024
Pittsburgh International Airport
Gas
14.4 MWOperating Allegheny, PAPJM Sep 20192021
Gans Solar Farm
Solar
14.0 MWOperating Fayette, PAPJM Apr 20192024
Dunbar Solar
Solar
14.0 MWOperating Fayette, PAPJM Apr 20192024
Stahlstown-Ligonier 25 kV
Solar
13.8 MWOperating Westmoreland, PAPJM Mar 20192024
Colice Hall Solar
Solar
12.0 MWOperating Hertford, NCPJM Mar 20192023
Gavin Unit No. 1
Coal
11.0 MWOperating Gallia, OHPJM Jul 20192025
Bartonsville Energy Facility
Solar
10.0 MWOperating Frederick, VAPJM Oct 20192024
Portland Station Unit 5
Gas
6.5 MWOperating Northampton, PAPJM Sep 20192020
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)