United States › Grid › Interconnection queues › Kentucky
SOLAR · PJMTurkey Creek Solar
Turkey Creek Solar is a 50.0 MW solar request built and operating in the PJM interconnection queue, in Garrard County, Kentucky, connecting to EKPC.
Request details
- Queue ID
- AE2-254
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- EKPC
- Connection point (POI)
- Garrard County-Tommy-Gooch 69 kV
- Location
- Garrard County, Kentucky
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 26 March 2019
- Proposed online date
- December 2022
- Came online
- October 2022
Location
Marker shows the centre of Garrard County; the queue data does not give exact sites.
Other requests in Garrard County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem