United States › Grid › Interconnection queues › New Jersey

BATTERY STORAGE · PJM

Viridity Energy Solutions Montague Storage

Viridity Energy Solutions Montague Storage is a 20.0 MW battery storage request built and operating in the PJM interconnection queue, in Sussex County, New Jersey, connecting to JCPL.

Queue statusOperating
  1. PlanningQueued Apr 2019 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-019
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Branchville-Holiday Lakes 34.5 kV
Location
Sussex County, New Jersey
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
6 April 2019
Proposed online date
January 2025
Came online
December 2024

Location

Marker shows the centre of Sussex County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Sussex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem