United States › Grid › Interconnection queues › New Jersey
SOLAR · PJMDurban Ave Solar
Durban Ave Solar is a 1.3 MW solar request built and operating in the PJM interconnection queue, in Sussex County, New Jersey, connecting to JCPL.
Request details
- Queue ID
- AE1-081
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- JCPL
- Connection point (POI)
- Landing 12.47 kV
- Location
- Sussex County, New Jersey
- Technology
- Solar: 1.3 MW
- Total requested
- 1.3 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Operational
- Entered queue
- 27 August 2018
- Proposed online date
- June 2021
- Came online
- September 2020
Location
Marker shows the centre of Sussex County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Sussex County
- Houses Corner StorageBattery storage · 20.0 MW · agreement signed
- Solar project AI1-122, Sussex CountySolar · 5.9 MW · in study
- Viridity Energy Solutions Montague StorageBattery storage · 20.0 MW · built
- VESI ‚Äì Andover Energy StorageBattery storage · 19.8 MW · built
- Frankford Solar FarmSolar · 10.0 MW · built
- Beaver Run Solar FarmSolar · 9.9 MW · built
- Roy Road Battery Storage FacilityBattery storage · 8.0 MW · built
- Wantage Solar FarmSolar · 7.5 MW · built
- Roy Road Battery Storage FacilityBattery storage · 6.0 MW · built
- Sussex County Land FillOther · 3.4 MW · built
- Augusta Solar FarmSolar · 3.0 MW · built
- Hydro project U2-064, Sussex CountyHydro · 1,000 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem