United States β€Ί Grid β€Ί Interconnection queues β€Ί Indiana

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Indiana, PJM

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown396,500 MW
Active in queue17.4 GW117 requests
Agreement signed6,500 MW39 requests
Withdrawn21040.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

39 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Sullivan Generating Station 1
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Sullivan Generating Station 2
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Mammoth South Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Mammoth Central II Energy Center
Solar
300 MWAgreement signed Pulaski, INPJM Sep 2020target 2028
Mayapple Solar
Solar
260 MWAgreement signed Pulaski, INPJM Sep 2020target 2027
Honey Creek Solar
Solar + storage
200 MWAgreement signed White, INPJM Feb 2020target 2027
Warren County Wind Energy Center
Onshore wind
200 MWAgreement signed INPJM Sep 2020target 2028
Black Prairie Solar Park
Solar
200 MWAgreement signed White, INPJM Sep 2019target 2027
Bottlebrush Solar
Solar
200 MWAgreement signed Lake, INPJM Jan 2019target 2028
Blackford Wind Energy Project
Onshore wind
200 MWAgreement signed Blackford, INPJM Sep 2019target 2026
Trade Post Solar Energy Center
Solar
200 MWAgreement signed Sullivan, INPJM Mar 2017target 2026
Moss Creek Solar
Solar
200 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Prairie Creek Wind
Onshore wind Β· Prairie Creek Wind, LLC
200 MWAgreement signed Blackford, INPJM Mar 2020target 2029
Lake Trout Solar
Solar + storage
200 MWAgreement signed Blackford, INPJM Sep 2019target 2028
Hoosier Line Solar
Solar
180 MWAgreement signed White, INPJM Sep 2019target 2027
Sculpin Solar
Solar
180 MWAgreement signed Dekalb, INPJM Aug 2019target 2028
Skycrest Solar Energy Center
Solar
155 MWAgreement signed Jay, INPJM Feb 2019target 2026
Blackford Solar Energy Project
Solar
150 MWAgreement signed Jay, INPJM Sep 2019target 2026
Riverstart Solar Park IV
Solar
150 MWAgreement signed Randolph, INPJM Sep 2017target 2025
Magley Solar Energy Center
Solar
135 MWAgreement signed Adams, INPJM Sep 2020target 2029
Riverstart Solar Park II
Solar
125 MWAgreement signed Randolph, INPJM Mar 2019target 2027
Bluestem Solar
Solar
125 MWAgreement signed Laporte, INPJM Mar 2020target 2027
Rainbow Trout
Solar + storage
120 MWAgreement signed Tippecanoe, INPJM Sep 2020target 2028
Elkhart County Solar Project
Solar
100 MWAgreement signed Elkhart, INPJM Mar 2019target 2026
Flatrock Creek Solar II
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Prairie Creek Wind Phase 2
Onshore wind Β· Prairie Creek Wind Farm II, LLC
100 MWAgreement signed Blackford, INPJM Sep 2020target 2029
Flatrock Creek Solar I
Solar
100 MWAgreement signed Allen, INPJM Mar 2020target 2029
Tillman Solar Park
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Sun Chief Solar Farm
Solar
100 MWAgreement signed Jay, INPJM Jul 2020target 2027
Hawthorn Solar
Solar
83.0 MWAgreement signed Delaware, INPJM Sep 2019target 2028
Fall Creek Energy Storage
Battery storage
80.0 MWAgreement signed Madison, INPJM Mar 2020target 2028
BR Solar Sheriff 1
Solar
75.0 MWAgreement signed Grant, INPJM Sep 2020target 2028
Flatrock Creek Storage I
Battery storage
50.0 MWAgreement signed Allen, INPJM Sep 2020target 2029
Trade Post Energy Storage
Battery storage
50.0 MWAgreement signed Sullivan, INPJM Mar 2019target 2028
Lake Trout Solar
Solar
45.0 MWAgreement signed Blackford, INPJM Mar 2020target 2028
New Jay PV & BESS
Solar + storage
39.0 MWAgreement signed Jay, INPJM Sep 2020target 2028
Maple Solar
Solar
35.0 MWAgreement signed Huntington, INPJM Mar 2019target 2028
Bitter Ridge Wind Farm
Onshore wind
12.6 MWAgreement signed Jay, INPJM May 2020target 2025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)