United States βΊ Grid βΊ Interconnection queues βΊ Illinois
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Illinois, PJM
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project AE1-222, Grundy County Gas |
2,563 MW | Withdrawn / abandoned |
| Gas project AC1-153, Grundy County Gas |
1,300 MW | Withdrawn / abandoned |
| Gas project AC1-067, Cook County Gas |
1,254 MW | Withdrawn / abandoned |
| Coal project Y2-095, Randolph County Coal |
1,211 MW | Withdrawn / abandoned |
| Gas project AA2-035, Grundy County Gas |
1,019 MW | Withdrawn / abandoned |
| Onshore wind project V4-074, Hancock County Onshore wind |
1,000 MW | Withdrawn / abandoned |
| Gas project AA1-048, Grundy County Gas |
800 MW | Withdrawn / abandoned |
| Coal project Q68, Christian County Coal |
726 MW | Withdrawn / abandoned |
| Coal project H20_CE12, Adams County Coal |
700 MW | Withdrawn / abandoned |
| Indeck-Elwood Energy Center Coal |
600 MW | Withdrawn / abandoned |
| Gas project U2-095, Lee County Gas |
600 MW | Withdrawn / abandoned |
| Coal project V2-008, Christian County Coal |
600 MW | Withdrawn / abandoned |
| Coal project Y2-116, Randolph County Coal |
600 MW | Withdrawn / abandoned |
| Byron to Wayne Thermal #1 Project Gas |
575 MW | Withdrawn / abandoned |
| Gas project AB1-091, Kankakee County Gas |
575 MW | Withdrawn / abandoned |
| Gas project AB1-086, Mclean County Gas |
575 MW | Withdrawn / abandoned |
| Gas project AB1-090, Lee County Gas |
575 MW | Withdrawn / abandoned |
| Onshore wind project AE1-193, Henry County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project S62, Lasalle County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project AE1-194, Will County Onshore wind |
500 MW | Withdrawn / abandoned |
| Onshore wind project U2-058, Christian County Onshore wind |
500 MW | Withdrawn / abandoned |
| Battery storage project AG1-298, Cook County Battery storage Β· Big Shoulders Storage LLC |
500 MW | Withdrawn / abandoned |
| Onshore wind project AE1-195, Will County Onshore wind |
500 MW | Withdrawn / abandoned |
| Pleasant Ridge Wind Farm Onshore wind |
500 MW | Withdrawn / abandoned |
| Gas project Z2-041, Mchenry County Gas |
455 MW | Withdrawn / abandoned |
| Onshore wind project W2-046, Livingston County Onshore wind |
450 MW | Withdrawn / abandoned |
| Gas project V1-022, Kendall County Gas |
380 MW | Withdrawn / abandoned |
| Gas project Y2-103, Lake County Gas |
360 MW | Withdrawn / abandoned |
| Solar + storage project AE1-198, Mchenry County Solar + storage |
357 MW | Withdrawn / abandoned |
| Nuclear project Y1-005, Lasalle County Nuclear |
350 MW | Withdrawn / abandoned |
| Onshore wind project T105, Livingston County Onshore wind |
350 MW | Withdrawn / abandoned |
| Garden Prairie Energy Facility Gas |
350 MW | Withdrawn / abandoned |
| Nuclear project W1-040, Lasalle County Nuclear |
350 MW | Withdrawn / abandoned |
| Solar + storage project AH1-755, Livingston County Solar + storage Β· Livingston County Solar, LLC |
330 MW | Withdrawn / abandoned |
| Onshore wind project AF2-003, Marshall County Onshore wind |
303 MW | Withdrawn / abandoned |
| Onshore wind project R79, Livingston County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project R78, Livingston County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project W1-030, Ford County Onshore wind |
300 MW | Withdrawn / abandoned |
| Gas project O27, Livingston County Gas |
300 MW | Withdrawn / abandoned |
| Onshore wind project W1-031, Ford County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project AD2-142, Will County Onshore wind |
300 MW | Withdrawn / abandoned |
| Battery storage project AI1-206 Battery storage |
300 MW | Withdrawn / abandoned |
| Bright Stalk WF Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project AD1-133, Grundy County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project AG1-399, Mclean County Onshore wind Β· Wapella Bluffs Wind Project, LLC |
300 MW | Withdrawn / abandoned |
| Top Crop Wind Farm Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project AH1-601, Lee County Solar |
300 MW | Withdrawn / abandoned |
| Battery storage project AI1-205 Battery storage |
300 MW | Withdrawn / abandoned |
| Solar project AG1-119, Dekalb County Solar Β· Leeward Renewable Energy Development, LLC |
300 MW | Withdrawn / abandoned |
| Onshore wind project AF1-318, Putnam County Onshore wind Β· SkyYield Wind Farm, LLC |
300 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)