Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Vineyard Mid-Atlantic West Offshore wind · Vineyard Mid-Atlantic LLC |
1,321 MW | In study |
| Bluepoint Wind 1 Offshore wind · Bluepoint Wind LLC |
1,310 MW | In study |
| Shallow Seam BESS Battery storage · Shallow Seam Energy Storage, LLC |
400 MW | In study |
| North Country Wind Onshore wind · NY North Country, LLC |
380 MW | In study |
| North Country Wind II Onshore wind · NY North Country, LLC |
380 MW | In study |
| Resilient NY Energy Storage Battery storage · Resilient NY Storage, LLC by Hanwha Energy USA Holdings Corporation, its Manager |
349 MW | In study |
| Stargazer II Solar + storage · RWE Solar Development, LLC |
325 MW | In study |
| Stargazer I Solar + storage · RWE Solar Development, LLC |
325 MW | In study |
| Blue Spruce Storage Battery storage · Blue Spruce Storage LLC |
300 MW | In study |
| Sugar Loaf Energy Storage I Battery storage · Hambletonian Energy Storage LLC |
300 MW | In study |
| Willard Storage Battery storage · Emeren US, LLC |
300 MW | In study |
| Swiss Valley Energy Storage Battery storage · Sawhall Energy Storage LLC |
300 MW | In study |
| Moonlight Flats Solar Solar · Moonlight Flats Solar Power, LLC |
250 MW | In study |
| Lighthouse Energy Storage Battery storage · GCI Lighthouse Energy Storage, LLC |
250 MW | In study |
| Kce NY 38 Battery storage · KCE NY 38, LLC |
250 MW | In study |
| East Setauket Storage II Battery storage · East Setauket Energy Storage, LLC |
248 MW | In study |
| Town Line Solar CSR Phase I Solar + storage · RWE Solar Development, LLC |
240 MW | In study |
| Erie Canal BESS Battery storage · RWE Solar Development, LLC |
230 MW | In study |
| Gemma Energy Storage Battery storage · Hanwha Q CELLS USA Corp. |
200 MW | In study |
| BPP NY Lansing BESS I Battery storage · BPP NY Lansing BESS I LLC |
200 MW | In study |
| Southern Tier Energy Center Battery storage · Southern Tier Energy Center, LLC |
200 MW | In study |
| NY125C - Little Salmon Solar Solar · Little Salmon Solar LLC |
200 MW | In study |
| Highbush Energy Storage Battery storage · Hanwha Q CELLS USA Corp. |
200 MW | In study |
| Wheelhouse Energy Storage Battery storage · NEER Interconnection Holdings, LLC |
200 MW | In study |
| Overlook Storage Battery storage · Origis Development LLC |
199 MW | In study |
| Battery Park Storage Battery storage · Battery Park Storage LLC |
190 MW | In study |
| Elevate Arthur Kill II Battery storage · Lighthouse Arthur Kill II, LLC |
180 MW | In study |
| Lockport Storage Battery storage · Origis Development LLC |
180 MW | In study |
| Kimberlite Solar Solar · Kimberlite Solar Power, LLC |
175 MW | In study |
| Brusselville Solar Energy Center Solar + storage · Brusselville Solar, LLC |
170 MW | In study |
| Basecamp BESS Battery storage · RWE Solar Development, LLC |
170 MW | In study |
| Maple Harvest Wind Onshore wind · Maple Harvest Wind |
162 MW | In study |
| Amsterdam Solar Solar · RWE Solar Development, LLC |
150 MW | In study |
| Alcazar 2 Battery storage · Terra-Gen Development Company, LLC |
150 MW | In study |
| Oakdale Battery Storage LLC Battery storage · BayWa r.e Projects LLC. |
150 MW | In study |
| Bay Breeze solar Solar · Bay Breeze Solar, LLC |
150 MW | In study |
| NY Chateaugay 0 Willis Rd Storage Battery storage · Chateauguay River, LLC |
150 MW | In study |
| Gowanus Energy Storage Battery storage · Astoria Generating Company, L.P. |
150 MW | In study |
| Aria Storage 2 Battery storage · Terra-Gen Development Company, LLC |
150 MW | In study |
| Valcour Storage Battery storage · Emeren US, LLC |
150 MW | In study |
| Arch 4 Battery storage · Terra-Gen Development Company, LLC |
150 MW | In study |
| Lincoln Park DG, LLC Battery storage · BayWa r.e Projects LLC. |
150 MW | In study |
| Kce NY 37 Battery storage · KCE NY 37, LLC |
150 MW | In study |
| Farmhouse BESS Battery storage · RWE Solar Development, LLC |
150 MW | In study |
| Ramadi Utility Storage Battery storage · Ramadi LLC |
140 MW | In study |
| Palladium Storage Battery storage · Palladium Storage LLC |
140 MW | In study |
| Fraser Energy Storage Battery storage · EDF Renewables Development, Inc. |
135 MW | In study |
| Marathon BESS Battery storage · Marathon Power |
135 MW | In study |
| Cohocton Solar + storage · ACE DevCo NC, LLC |
130 MW | In study |
| Port Morris Energy Storage Battery storage · The NY Power Authority |
130 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)436 · 104.7 GW
- MISO (Midcontinent)290 · 62.9 GW
- West (non-ISO utilities)192 · 45.5 GW
- Southeast (non-ISO utilities)178 · 35.0 GW
- SPP (Southwest Power Pool)81 · 18.0 GW
- NYISO (New York)89 · 15.6 GW
- ISO-NE (New England)15 · 3,285 MW
- PJM (Mid-Atlantic, Midwest)2 · 95.0 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)