πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown43582.2 GW
Active in queue82.2 GW435 requests
Agreement signed881 MW6 requests
Withdrawn56794.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

435 requests Β· page 1 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J1813, Desoto County
Gas
1,005 MWIn study Desoto, MSMISO Jul 2022target 2002
Solar project J2186, Fulton County
Solar
821 MWIn study Fulton, ILMISO Jun 2022target 2024
Replacing 710 MW of coal generation with solar at Sherco Unit 2; Sherco Unit 2
Other
710 MWIn study Sherburne, MNMISO Dec 20222024
Solar project J2846, Pulaski County
Solar
700 MWIn study Pulaski, INMISO Sep 2022target 2025
Solar project J2477, Crittenden County
Solar
600 MWIn study Crittenden, ARMISO Sep 2022target 2026
Solar project J2519, Richland Parish County
Solar
600 MWIn study Richland Parish, LAMISO Sep 2022target 2026
Solar + storage project J3075, Sullivan County
Solar + storage
560 MWIn study Sullivan, INMISO Sep 2022target 2025
Solar project J2478, Craighead County
Solar
550 MWIn study Craighead, ARMISO Sep 2022target 2026
Solar project J2395, Calhoun County
Solar
500 MWIn study Calhoun, ARMISO Sep 2022target 2025
Solar project J2708, Ouachita Parish County
Solar
500 MWIn study Ouachita Parish, LAMISO Sep 2022target 2027
Other project J2694, Christian County
Other
500 MWIn study Christian, ILMISO Sep 2022target 2027
Solar project J2704, Ouachita Parish County
Solar
500 MWIn study Ouachita Parish, LAMISO Sep 2022target 2027
Solar + storage project J3076, Wabash County
Solar + storage
500 MWIn study Wabash, ILMISO Sep 2022target 2025
Solar project J3192, Jackson County
Solar
500 MWIn study Jackson, ARMISO Sep 2022target 2025
Wind + storage project J2690, Washington County
Wind + storage
500 MWIn study Washington, ILMISO Sep 2022target 2027
Solar project J2696, Mississippi County
Solar
500 MWIn study Mississippi, ARMISO Sep 2022target 2027
Battery storage project J2590, Huron County
Battery storage
500 MWIn study Huron, MIMISO Sep 2022target 2025
Other project J2171, Perry County
Other
500 MWIn study Perry, ILMISO Mar 2022target 2024
Onshore wind project J2841, Independence County
Onshore wind
500 MWIn study Independence, ARMISO Sep 2022target 2025
Other project J3163, Cass County
Other
479 MWIn study Cass, NDMISO Jul 2022target 2028
Solar + storage project J3030, Jefferson County
Solar + storage
450 MWIn study Jefferson, ARMISO Sep 2022target 2027
Solar + storage project J2914, St. Tammany Parish County
Solar + storage
450 MWIn study St. Tammany Parish, LAMISO Sep 2022target 2026
Solar project J2966, Quitman County
Solar
450 MWIn study Quitman, MSMISO Sep 2022target 2025
Replacing 300 MW of existing coal generation with BESS; Edgewater 5
Other
423 MWIn study MISO Feb 2022target 2025
Battery storage project J2496, White County
Battery storage
400 MWIn study White, INMISO Sep 2022target 2026
Solar project J2088, Lee County
Solar
400 MWIn study Lee, ARMISO Jul 2022target 2027
Solar project J2931, Henderson County
Solar
400 MWIn study Henderson, KYMISO Sep 2022target 2025
Solar + storage project J2907, Grant County
Solar + storage
400 MWIn study Grant, ARMISO Sep 2022target 2026
Solar project J2396, Calhoun County
Solar
400 MWIn study Calhoun, ARMISO Sep 2022target 2025
Wind + storage project J3015, Iroquois County
Wind + storage
400 MWIn study Iroquois, ILMISO Sep 2022target 2027
Surplus; G876/G877
Wind + storage
400 MWIn study Mclean, ILMISO Sep 2022target 2025
Solar project J2107, Portage County
Solar
399 MWIn study Portage, WIMISO Jun 2022target 2024
Solar project J2099, Portage County
Solar
399 MWIn study Portage, WIMISO Jun 2022target 2024
Solar project J2185, Portage County
Solar
399 MWIn study Portage, WIMISO Jun 2022target 2024
Solar project J2866, Nevada County
Solar
375 MWIn study Nevada, ARMISO Sep 2022target 2027
Solar project J2865, Ouachita County
Solar
375 MWIn study Ouachita, ARMISO Sep 2022target 2027
Solar project J2864, Nevada County
Solar
375 MWIn study Nevada, ARMISO Sep 2022target 2027
Solar project J3040, Ouachita County
Solar
365 MWIn study Ouachita, ARMISO Sep 2022target 2027
Solar + storage project J2390, Fulton County
Solar + storage
350 MWIn study Fulton, ILMISO Sep 2022target 2026
Gas project J2944, Portage County
Gas
350 MWIn study Portage, WIMISO Sep 2022target 2027
Gas project J2945, Washington County
Gas
350 MWIn study Washington, IAMISO Sep 2022target 2027
Solar project J3209, Rapides Parish County
Solar
350 MWIn study Rapides Parish, LAMISO Sep 2022target 2026
Solar project J2603, Mason County
Solar
320 MWIn study Mason, ILMISO Sep 2022target 2026
Battery storage project J2469, Linn County
Battery storage
300 MWIn study Linn, IAMISO Sep 2022target 2027
Onshore wind project J2369, Taylor County
Onshore wind
300 MWIn study Taylor, IAMISO Sep 2022target 2030
Battery storage project J2716, Dakota County
Battery storage
300 MWIn study Dakota, MNMISO Sep 2022target 2027
Solar project J3131, Columbia County
Solar
300 MWIn study Columbia, ARMISO Sep 2022target 2026
Solar project J1730, Dunn County
Solar
300 MWUnder construction Dunn, WIMISO Mar 2022target 2027
Solar project J2482, Crittenden County
Solar
300 MWIn study Crittenden, ARMISO Sep 2022target 2026
Solar project J2252, Jackson County
Solar
300 MWIn study Jackson, ARMISO Jul 2022target 2027
Page 1 of 9

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)