United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in MISO (Midcontinent) (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown283,509 MW
Active in queue1,433 MW15 requests
Agreement signed1,011 MW10 requests
Withdrawn18525.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

28 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J541, Schuyler County
Onshore wind
400 MWOperating Schuyler, MOMISO Jan 20162020
Onshore wind project J757, Morgan County
Onshore wind
304 MWOperating Morgan, ILMISO Nov 20162021
Onshore wind project J756, Logan County
Onshore wind
202 MWOperating Logan, ILMISO Nov 20162020
Onshore wind project J728, Isabella County
Onshore wind
200 MWOperating Isabella, MIMISO Nov 20162020
Onshore wind project J717, Isabella County
Onshore wind
200 MWOperating Isabella, MIMISO Sep 20162020
Onshore wind project J587, Lincoln County
Onshore wind
200 MWOperating Lincoln, MNMISO May 20162020
Onshore wind project J748, Plymouth County
Onshore wind
200 MWOperating Plymouth, IAMISO Nov 20162021
Onshore wind project J583, Audubon County
Onshore wind
200 MWOperating Audubon, IAMISO May 20162021
Solar project J758, Calhoun County
Solar
200 MWOperating Calhoun, MIMISO Nov 20162022
Onshore wind project J589, Gratiot County
Onshore wind
149 MWOperating Gratiot, MIMISO May 20162018
Onshore wind project J555, Poweshiek County
Onshore wind
140 MWOperating Poweshiek, IAMISO Mar 20162017
Gas project J703, Marquette County
Gas
128 MWOperating Marquette, MIMISO Sep 20162018
Onshore wind project J611, Nodaway County
Onshore wind
110 MWOperating Nodaway, MOMISO May 20162020
Solar project J620, Chicot County
Solar
100 MWOperating Chicot, ARMISO May 20162019
Solar project J679, Carroll County
Solar
100 MWOperating Carroll, MSMISO Jul 20162021
Onshore wind project J752, Tuscola County
Onshore wind
100 MWOperating Tuscola, MIMISO Nov 20162019
Onshore wind project J652, Lafayette County
Onshore wind
98.0 MWOperating Lafayette, WIMISO Jul 20162017
Onshore wind project J590, Palo Alto County
Onshore wind
90.0 MWOperating Palo Alto, IAMISO May 20162019
Solar project J759, Spencer County
Solar
70.0 MWOperating Spencer, INMISO Nov 20162020
Onshore wind project J614, Howard County
Onshore wind
66.0 MWOperating Howard, IAMISO May 20162018
Gas project J734, Ford County
Gas
57.1 MWOperating Ford, ILMISO Nov 20162017
Gas project J704, Baraga County
Gas
54.9 MWOperating Baraga, MIMISO Sep 20162018
Solar project J683, West Baton Rouge Parish, La County
Solar
50.0 MWOperating West Baton Rouge Parish, La, LAMISO Jul 20162020
Gas project J540, Kalkaska County
Gas
48.6 MWOperating Kalkaska, MIMISO Jan 2016
Gas project J760, Rock County
Gas
30.0 MWOperating Rock, WIMISO Nov 20162019
Onshore wind project J558, Pipestone County
Onshore wind
9.2 MWOperating Pipestone, MNMISO Apr 20162017
Solar project J554, Dodge County
Solar
1.0 MWOperating Dodge, MNMISO Mar 20162016
Solar project J557, Delta County
Solar
0.9 MWOperating Delta, MIMISO Apr 20162016

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)