United States › Grid › Interconnection queues › Michigan

GAS · MISO

Gas project J704, Baraga County

Gas project J704, Baraga County is a 54.9 MW gas request built and operating in the MISO interconnection queue, in Baraga County, Michigan, connecting to American Transmission Co..

Queue statusOperating
  1. PlanningQueued Sep 2016 (completed)
  2. ConsentedDec 2017 (completed)
  3. Construction (completed)
  4. OperatingDec 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J704
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
M38 Substation 138kV
Location
Baraga County, Michigan
Technology
Gas: 54.9 MW
Total requested
54.9 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
8 September 2016
Agreement signed
19 December 2017
Proposed online date
December 2018
Came online
December 2018

Location

Marker shows the centre of Baraga County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Baraga County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem