United States βΊ Grid βΊ Interconnection queues βΊ Michigan
ONSHORE WIND Β· MISOOnshore wind project J1138, Baraga County
Onshore wind project J1138, Baraga County is a 70.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Baraga County, Michigan, connecting to American Transmission Co..
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedDec 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1138
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- American Transmission Co.
- Connection point (POI)
- M38 138 kV Substation
- Location
- Baraga County, Michigan
- Technology
- Wind: 70.0 MW
- Total requested
- 70.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 March 2018
- Proposed online date
- September 2020
- Withdrawn
- December 2018
Location
Marker shows the centre of Baraga County; the queue data does not give exact sites.
Other requests in Baraga County
- Gas project J3800, Baraga CountyGas Β· 1.8 MW Β· in study
- Gas project J704, Baraga CountyGas Β· 54.9 MW Β· built
- Other project G343, Baraga CountyOther Β· 20.0 MW Β· built
- Gas project G342, Baraga CountyGas Β· 18.0 MW Β· built
- Onshore wind project J711, Baraga CountyOnshore wind Β· 130 MW Β· withdrawn
- Solar + storage project J3648, Baraga CountySolar + storage Β· 120 MW Β· withdrawn
- Onshore wind project J879, Baraga CountyOnshore wind Β· 70.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem