Solar project J1226, Lenawee County Solar |
200 MW | Under construction |
Lenawee, MI | MISO |
Apr 2019 | target 2024 |
Solar project J1196, Sanilac County Solar |
200 MW | Agreement signed |
Sanilac, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1379, Montcalm County Solar |
200 MW | Agreement signed |
Montcalm, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1255, Ionia County Solar |
200 MW | Under construction |
Ionia, MI | MISO |
Apr 2019 | target 2025 |
Onshore wind project J1292, Ionia County Onshore wind |
198 MW | Agreement signed |
Ionia, MI | MISO |
Apr 2019 | target 2024 |
Solar project J1297, Shiawassee County Solar |
170 MW | Under construction |
Shiawassee, MI | MISO |
Apr 2019 | target 2024 |
Solar project J1224, Washtenaw County Solar |
170 MW | Under construction |
Washtenaw, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1320, Branch County Solar |
150 MW | Agreement signed |
Branch, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1203, Genesee County Solar |
125 MW | Under construction |
Genesee, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1310, Jackson County Solar |
125 MW | Under construction |
Jackson, MI | MISO |
Apr 2019 | target 2024 |
Solar project J1389, Saginaw County Solar |
120 MW | Agreement signed |
Saginaw, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1248, Calhoun County Solar |
100 MW | Agreement signed |
Calhoun, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1430, Calhoun County Solar |
100 MW | Agreement signed |
Calhoun, MI | MISO |
Apr 2019 | 2023 |
Solar project J1375, Muskegon County Solar |
100 MW | Under construction |
Muskegon, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1331, St. Clair County Solar |
100 MW | Agreement signed |
St. Clair, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1472, Jackson County Solar |
100 MW | Agreement signed |
Jackson, MI | MISO |
Apr 2019 | target 2024 |
Solar project J1251, Marquette County Solar |
100 MW | Under construction |
Marquette, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1399, Ingham County Solar |
90.0 MW | Agreement signed |
Ingham, MI | MISO |
Apr 2019 | target 2025 |
Solar project J1210, Iosco County Solar |
50.0 MW | Agreement signed |
Iosco, MI | MISO |
Apr 2019 | target 2025 |
Gas project J1262, Wayne County Gas |
25.0 MW | Agreement signed |
Wayne, MI | MISO |
Apr 2019 | target 2022 |
Battery storage project J1329, Washtenaw County Battery storage |
20.0 MW | Under construction |
Washtenaw, MI | MISO |
Apr 2019 | target 2025 |