United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Illinois, MISO (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8817.5 GW
Active in queue17.5 GW88 requests
Agreement signed0.0 MW0 requests
Withdrawn6711.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

88 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2186, Fulton County
Solar
821 MWIn study Fulton, ILMISO Jun 2022target 2024
Other project J2694, Christian County
Other
500 MWIn study Christian, ILMISO Sep 2022target 2027
Solar + storage project J3076, Wabash County
Solar + storage
500 MWIn study Wabash, ILMISO Sep 2022target 2025
Wind + storage project J2690, Washington County
Wind + storage
500 MWIn study Washington, ILMISO Sep 2022target 2027
Other project J2171, Perry County
Other
500 MWIn study Perry, ILMISO Mar 2022target 2024
Wind + storage project J3015, Iroquois County
Wind + storage
400 MWIn study Iroquois, ILMISO Sep 2022target 2027
Surplus; G876/G877
Wind + storage
400 MWIn study Mclean, ILMISO Sep 2022target 2025
Solar + storage project J2390, Fulton County
Solar + storage
350 MWIn study Fulton, ILMISO Sep 2022target 2026
Solar project J2603, Mason County
Solar
320 MWIn study Mason, ILMISO Sep 2022target 2026
Battery storage project J2647, Franklin County
Battery storage
300 MWIn study Franklin, ILMISO Sep 2022target 2028
Solar project J2556, Whiteside County
Solar
300 MWIn study Whiteside, ILMISO Sep 2022target 2026
Wind + storage project J3027, Stark County
Wind + storage
300 MWIn study Stark, ILMISO Sep 2022target 2027
Battery storage project J3216, Peoria County
Battery storage
300 MWIn study Peoria, ILMISO Sep 2022target 2027
Solar project J3012, Coles County
Solar
287 MWIn study Coles, ILMISO Sep 2022target 2026
Solar project J2565, Iroquois County
Solar
265 MWIn study Iroquois, ILMISO Sep 2022target 2026
Onshore wind project J3078, Peoria County
Onshore wind
252 MWIn study Peoria, ILMISO Sep 2022target 2026
Solar project J2793, Saline County
Solar
250 MWIn study Saline, ILMISO Sep 2022target 2026
Solar project J2973, Christian County
Solar
250 MWIn study Christian, ILMISO Sep 2022target 2026
Solar project J3074, Randolph County
Solar
250 MWIn study Randolph, ILMISO Sep 2022target 2025
Solar + storage project J2267, Williamson County
Solar + storage
250 MWIn study Williamson, ILMISO Mar 2022target 2025
Solar project J2922, Jasper County
Solar
250 MWIn study Jasper, ILMISO Sep 2022target 2028
Onshore wind project J2275, Peoria County
Onshore wind
250 MWIn study Peoria, ILMISO Mar 2022target 2025
Solar project J2662, Cumberland County
Solar
250 MWIn study Cumberland, ILMISO Sep 2022target 2026
Solar project J2554, Putnam County
Solar
220 MWIn study Putnam, ILMISO Sep 2022target 2026
Solar project J2403, Johnson County
Solar
200 MWIn study Johnson, ILMISO Sep 2022target 2025
Battery storage project J3031, Jefferson County
Battery storage
200 MWIn study Jefferson, ILMISO Sep 2022target 2026
Onshore wind project J2049, Shelby County
Onshore wind
200 MWIn study Shelby, ILMISO Mar 2022target 2025
Battery storage project J2402, Johnson County
Battery storage
200 MWIn study Johnson, ILMISO Sep 2022target 2025
Onshore wind project J2614, Henry County
Onshore wind
200 MWIn study Henry, ILMISO Sep 2022target 2026
Solar + storage project J3080, Pulaski County
Solar + storage
200 MWIn study Pulaski, ILMISO Sep 2022target 2025
Onshore wind project J1926, Tazewell County
Onshore wind
200 MWIn study Tazewell, ILMISO Mar 2022target 2025
Battery storage project J2587, Edgar County
Battery storage
200 MWIn study Edgar, ILMISO Sep 2022target 2025
Battery storage project J2607, Montgomery County
Battery storage
200 MWIn study Montgomery, ILMISO Sep 2022target 2026
Solar project J3095, Ford County
Solar
200 MWIn study Ford, ILMISO Sep 2022target 2025
Solar + storage project J2388, Macon County
Solar + storage
200 MWIn study Macon, ILMISO Sep 2022target 2026
Onshore wind project J2938, Knox County
Onshore wind
200 MWIn study Knox, ILMISO Sep 2022target 2025
Battery storage project J2998, St. Clair County
Battery storage
200 MWIn study St. Clair, ILMISO Sep 2022target 2025
Battery storage project J2379, Clay County
Battery storage
200 MWIn study Clay, ILMISO Sep 2022target 2026
Battery storage project J2532, Sangamon County
Battery storage
200 MWIn study Sangamon, ILMISO Sep 2022target 2026
Onshore wind project J2963, Mason County
Onshore wind
200 MWIn study Mason, ILMISO Sep 2022target 2025
Battery storage project J2575, Tazewell County
Battery storage
198 MWIn study Tazewell, ILMISO Sep 2022target 2027
Solar project J2334, Montgomery County
Solar
195 MWIn study Montgomery, ILMISO Sep 2022target 2027
Solar project J2136, Iroquois County
Solar
191 MWIn study Iroquois, ILMISO Mar 2022target 2024
Solar project J2937, Montgomery County
Solar
186 MWIn study Montgomery, ILMISO Sep 2022target 2025
Solar project J2656, Macon County
Solar
180 MWIn study Macon, ILMISO Sep 2022target 2026
Solar + storage project J3003, Mason County
Solar + storage
180 MWIn study Mason, ILMISO Sep 2022target 2025
Solar project J3167, Fulton County
Solar
180 MWIn study Fulton, ILMISO Sep 2022target 2026
Onshore wind project J2247, Marshall County
Onshore wind
178 MWIn study Marshall, ILMISO Mar 2022target 2024
Solar project J2258, Adams County
Solar
175 MWIn study Adams, ILMISO Mar 2022target 2024
Solar project J3064, Perry County
Solar
157 MWIn study Perry, ILMISO Sep 2022target 2026
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)