Withdrawn queue requests in Arkansas, MISO

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown27947.5 GW
Active in queue33.3 GW142 requests
Agreement signed1,150 MW8 requests
Withdrawn27947.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

279 requests Β· page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J433, Union County
Gas
1,270 MWWithdrawn / abandoned Union, ARMISO Jan 2015
Gas project J4111, Hot Spring County
Gas
650 MWWithdrawn / abandoned Hot Spring, ARMISO Oct 2025target 2030
Solar + storage project J2717, Hot Spring County
Solar + storage
600 MWWithdrawn / abandoned Hot Spring, ARMISO Sep 2022target 2029
Solar project J3530, Saline County
Solar
500 MWWithdrawn / abandoned Saline, ARMISO Apr 2024target 2028
Solar project J2785, Calhoun County
Solar
500 MWWithdrawn / abandoned Calhoun, ARMISO Sep 2022target 2026
Solar project J2758, Jefferson County
Solar
500 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2025
Solar project J2399, Craighead County
Solar
500 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2025
Solar project J3626, Craighead County
Solar
500 MWWithdrawn / abandoned Craighead, ARMISO Apr 2024target 2027
Solar project J3426, Chicot County
Solar
500 MWWithdrawn / abandoned Chicot, ARMISO Mar 2024target 2028
Solar project J3386, Calhoun County
Solar
500 MWWithdrawn / abandoned Calhoun, ARMISO Apr 2024target 2028
Solar project J2682, Jackson County
Solar
500 MWWithdrawn / abandoned Jackson, ARMISO Sep 2022target 2025
Solar project J2452, Cleveland County
Solar
500 MWWithdrawn / abandoned Cleveland, ARMISO Sep 2022target 2026
Other project J319, Pope County
Other
500 MWWithdrawn / abandoned Pope, ARMISO Dec 2013target 2018
Solar project J2936, Jackson County
Solar
500 MWWithdrawn / abandoned Jackson, ARMISO Sep 2022target 2025
Solar project J3427, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARMISO Mar 2024target 2028
Solar project J3937, Dallas County
Solar
500 MWWithdrawn / abandoned Dallas, ARMISO Apr 2025target 2030
Solar project J1097, Lonoke County
Solar
500 MWWithdrawn / abandoned Lonoke, ARMISO Mar 2018target 2021
Battery storage project J3023, Hot Spring County
Battery storage
400 MWWithdrawn / abandoned Hot Spring, ARMISO Sep 2022target 2026
Solar project J3303, Prairie County
Solar
400 MWWithdrawn / abandoned Prairie, ARMISO Apr 2024target 2027
Solar project J3388, Calhoun County
Solar
400 MWWithdrawn / abandoned Calhoun, ARMISO Apr 2024target 2028
Solar project J3540, Monroe County
Solar
400 MWWithdrawn / abandoned Monroe, ARMISO Apr 2024target 2028
Solar project J3711, Calhoun County
Solar
400 MWWithdrawn / abandoned Calhoun, ARMISO Apr 2024target 2029
Solar + storage project J3110, Craighead County
Solar + storage
400 MWWithdrawn / abandoned Craighead, ARMISO Sep 2022target 2026
Solar project J2640, Calhoun County
Solar
395 MWWithdrawn / abandoned Calhoun, ARMISO Sep 2022target 2025
Solar project J2510, Jefferson County
Solar
350 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2026
Solar project J3304, Clark County
Solar
350 MWWithdrawn / abandoned Clark, ARMISO Apr 2024target 2027
Solar project J3570, Cross County
Solar
300 MWWithdrawn / abandoned Cross, ARMISO Apr 2024target 2028
Solar project J2516, Jefferson County
Solar
300 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2026
Solar project J3048, Crawford County
Solar
300 MWWithdrawn / abandoned Crawford, ARMISO Sep 2022target 2027
Solar project J3575, Mississippi County
Solar
300 MWWithdrawn / abandoned Mississippi, ARMISO Apr 2024target 2028
Solar + storage project J3583, Lonoke County
Solar + storage
300 MWWithdrawn / abandoned Lonoke, ARMISO Apr 2024target 2028
Solar project J3802, Phillips County
Solar
300 MWWithdrawn / abandoned Phillips, ARMISO Apr 2024target 2028
Solar project J3569, Poinsett County
Solar
300 MWWithdrawn / abandoned Poinsett, ARMISO Apr 2024target 2028
Solar project J2090, Crittenden County
Solar
300 MWWithdrawn / abandoned Crittenden, ARMISO Jul 2022target 2026
Solar + storage project J3747, Lonoke County
Solar + storage
300 MWWithdrawn / abandoned Lonoke, ARMISO Apr 2024target 2028
Solar project J3171, Drew County
Solar
300 MWWithdrawn / abandoned Drew, ARMISO Sep 2022target 2026
Solar project J1078, Mississippi County
Solar
300 MWWithdrawn / abandoned Mississippi, ARMISO Mar 2018target 2021
Solar project J2386, Poinsett County
Solar
300 MWWithdrawn / abandoned Poinsett, ARMISO Sep 2022target 2026
Solar project J2515, Jefferson County
Solar
300 MWWithdrawn / abandoned Jefferson, ARMISO Sep 2022target 2026
Other project J1283, Jefferson County
Other
270 MWWithdrawn / abandoned Jefferson, ARMISO Apr 2019target 2023
Solar project J3773, Drew County
Solar
265 MWWithdrawn / abandoned Drew, ARMISO Apr 2024target 2028
Onshore wind project J4027, Clay County
Onshore wind
250 MWWithdrawn / abandoned Clay, ARMISO May 2025target 2030
Solar project J2631, Arkansas County
Solar
250 MWWithdrawn / abandoned Arkansas, ARMISO Sep 2022target 2025
Solar project J3571, Poinsett County
Solar
250 MWWithdrawn / abandoned Poinsett, ARMISO Apr 2024target 2028
Solar project J2850, Chicot County
Solar
250 MWWithdrawn / abandoned Chicot, ARMISO Sep 2022target 2027
Solar project J2028, Crittenden County
Solar
250 MWWithdrawn / abandoned Crittenden, ARMISO Aug 2021target 2024
Solar project J3270, Phillips County
Solar
250 MWWithdrawn / abandoned Phillips, ARMISO Apr 2024target 2028
Solar project J3511, Arkansas County
Solar
250 MWWithdrawn / abandoned Arkansas, ARMISO Apr 2024target 2028
Battery storage project J3580, Mississippi County
Battery storage
250 MWWithdrawn / abandoned Mississippi, ARMISO Apr 2024target 2028
Solar + storage project J2649, Lee County
Solar + storage
250 MWWithdrawn / abandoned Lee, ARMISO Sep 2022target 2027
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)