United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in CAISO (California)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown23437.6 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

234 requests Β· page 1 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Mcfarland Solar
Solar + storage
935 MWOperating Yuma, AZCAISO Apr 20152025
CPV Sentinel (Fka Intergen Ocotillo)
Gas
866 MWOperating Riverside, CACAISO Jun 20002013
Dracker Solar
Solar + storage
825 MWOperating Riverside, CACAISO Jan 2008target 2012
Inland Empire Energy Center
Gas
810 MWOperating Riverside, CACAISO Dec 20042010
Genesis Mccoy
Solar + storage
730 MWOperating Riverside, CACAISO Apr 20072021
CPV Colusa
Gas
715 MWOperating Colusa, CACAISO Feb 20052010
Arlington
Solar + storage
652 MWOperating Riverside, CACAISO Apr 20152023
Slate
Solar + storage
617 MWOperating Kings, CACAISO Apr 20152022
Gateway Generating Facility (Fka Contra Costa Power Plant Project)
Gas
590 MWOperating Contra Costa, CACAISO Feb 20002009
NRG El Segundo - TOT041
Gas
570 MWOperating Los Angeles, CACAISO Oct 20002013
Edsan 2
Solar + storage
553 MWOperating Kern, CACAISO May 20172023
Otay Mesa Generating Project
Gas
550 MWOperating San Diego, CACAISO Nov 19992009
CPC East
Onshore wind
550 MWOperating Kern, CACAISO Mar 20062012
Rexford Solar Farm
Solar + storage
540 MWOperating Tulare, CACAISO Apr 20182025
Desert Sunlight PV II
Solar + storage
530 MWOperating Riverside, CACAISO Nov 2006target 2010
Palomar Energy Project
Gas
521 MWOperating San Diego, CACAISO Aug 20002005
Blythe Energy Project Phase I
Gas
520 MWOperating Riverside, CACAISO Jul 20022010
Almasol
Solar + storage
507 MWOperating Riverside, CACAISO May 20082022
Walnut Creek Energy Park - Phase 1
Gas
501 MWOperating Los Angeles, CACAISO May 20052013
Dallas Energy Storage
Battery storage
500 MWOperating Monterey, CACAISO Apr 20182021
Voyager Wind 2
Onshore wind
500 MWOperating Kern, CACAISO Aug 20062021
Desert Sunlight PV I
Solar + storage
480 MWOperating Riverside, CACAISO Nov 2006target 2008
Westlands Solar Blue
Solar + storage
477 MWOperating Kings, CACAISO Apr 20152023
Silver State South Solar Project
Solar + storage
430 MWOperating Clark, NVCAISO Jun 20082016
Panoche Energy Center C11
Gas
427 MWOperating Fresno, CACAISO Apr 20182024
Kola
Battery storage
418 MWOperating Alameda, CACAISO May 2016target 2020
Marvel
Battery storage
406 MWOperating Riverside, CACAISO May 20162024
Panoche Energy Center
Gas
401 MWOperating Fresno, CACAISO Dec 20042009
Yellow Pine 2
Solar + storage
400 MWOperating Clark, NVCAISO May 2016target 2019
Edsan 1
Solar + storage
384 MWOperating Kern, CACAISO May 20162023
Plano Storage
Battery storage
365 MWOperating Monterey, CACAISO May 20192023
Russell City Energy Center
Gas
354 MWOperating Alameda, CACAISO Dec 20042013
Proxima Solar
Solar + storage
352 MWOperating Stanislaus, CACAISO May 20162024
Bateria Del Sur
Battery storage
350 MWOperating Imperial, CACAISO Apr 20182025
Crimson
Battery storage
350 MWOperating Riverside, CACAISO Apr 20152022
California Flats Solar
Solar + storage
340 MWOperating Monterey, CACAISO Apr 20122019
Willy 9
Solar + storage
338 MWOperating Kern, CACAISO May 20162025
Blythe Mesa Solar
Solar + storage
336 MWOperating Riverside, CACAISO Feb 20102022
Sol Catcher BESS
Solar + storage
335 MWOperating Riverside, CACAISO May 20162024
Solar Star 1
Solar
310 MWOperating Kern, CACAISO May 20082015
Pio Pico Energy Center
Gas
308 MWOperating San Diego, CACAISO Feb 20102016
Daggett Solar 2
Solar + storage
300 MWOperating San Bernardino, CACAISO May 20162023
Desert Stateline Project
Solar
300 MWOperating San Bernardino, CACAISO Jan 20072016
Agua Caliente
Solar
290 MWOperating Yuma, AZCAISO Jun 20082014
Garland
Solar + storage
288 MWOperating Kern, CACAISO Apr 20132021
Chestnut Westside
Solar + storage
287 MWOperating Kings, CACAISO Apr 20152023
Lodi Energy Center
Gas
280 MWOperating San Joaquin, CACAISO Oct 20072012
Solar Star 2
Solar
276 MWOperating Kern, CACAISO May 20082015
Re Tranquillity
Solar + storage
272 MWOperating Fresno, CACAISO Jul 20102022
Fifth Standard Solar
Solar + storage
267 MWOperating Fresno, CACAISO Apr 20132023
Page 1 of 5

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)