United States › Grid › Interconnection queues › California

GAS · CAISO

CPV Sentinel (Fka Intergen Ocotillo)

CPV Sentinel (Fka Intergen Ocotillo) is a 866 MW gas request built and operating in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Jun 2000 (completed)
  2. ConsentedNov 2019 (completed)
  3. Construction (completed)
  4. OperatingJun 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
3
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Devers Substation 230kV Bus
Location
Riverside County, California
Technology
Gas: 850 MW · Battery: 16.0 MW
Total requested
866 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
14 June 2000
Agreement signed
21 November 2019
Proposed online date
January 2004
Came online
June 2013

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Riverside County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem