United States › Grid › Interconnection queues › California
GAS · CAISOCPV Sentinel (Fka Intergen Ocotillo)
CPV Sentinel (Fka Intergen Ocotillo) is a 866 MW gas request built and operating in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.
Request details
- Queue ID
- 3
- Grid region
- CAISO (California)
- Utility / transmission owner
- SCE
- Connection point (POI)
- Devers Substation 230kV Bus
- Location
- Riverside County, California
- Technology
- Gas: 850 MW · Battery: 16.0 MW
- Total requested
- 866 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 14 June 2000
- Agreement signed
- 21 November 2019
- Proposed online date
- January 2004
- Came online
- June 2013
Location
Marker shows the centre of Riverside County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Riverside County
- OberonSolar + storage · 1,037 MW · agreement signed
- Grace Energy CenterSolar + storage · 1,017 MW · agreement signed
- EasleySolar + storage · 940 MW · agreement signed
- Athos Power PlantSolar + storage · 908 MW · agreement signed
- Lycan SolarSolar + storage · 800 MW · agreement signed
- Calypso SolarSolar + storage · 800 MW · agreement signed
- Menifee Power BankBattery storage · 680 MW · agreement signed
- Twin Palms SolarSolar + storage · 576 MW · agreement signed
- RedondaSolar + storage · 542 MW · agreement signed
- CobaltSolar + storage · 513 MW · agreement signed
- Double Butte StorageBattery storage · 508 MW · agreement signed
- Lake Elsinore Advanced Pumped Storage ProjectBattery storage · 500 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem