United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Almasol

Almasol is a 507 MW solar + storage request built and operating in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued May 2008 (completed)
  2. ConsentedDec 2010 (completed)
  3. Construction (completed)
  4. OperatingJun 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
365
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Red Bluff Substation 230kV
Location
Riverside County, California
Technology
Solar: 457 MW · Battery: 50.0 MW
Total requested
507 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
12 May 2008
Agreement signed
14 December 2010
Proposed online date
December 2013
Came online
June 2022

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Riverside County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem