SOLAR Β· CAISOSolar Star 1
Solar Star 1 is a 310 MW solar request built and operating in the CAISO interconnection queue, in Kern County, California, connecting to SCE.
Request details
- Queue ID
- 407
- Grid region
- CAISO (California)
- Utility / transmission owner
- SCE
- Connection point (POI)
- Cottonwind-Whirlwind 230kV line
- Location
- Kern County, California
- Technology
- Solar: 310 MW
- Total requested
- 310 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Operational
- Entered queue
- 30 May 2008
- Agreement signed
- 8 November 2011
- Proposed online date
- July 2012
- Came online
- June 2015
Location
Marker shows the centre of Kern County; the queue data does not give exact sites.
Power plants in California Β· Transmission lines in California
Other requests in Kern County
- Solar project Q03, Kern CountySolar Β· 250 MW Β· under construction
- Sanborn Hybrid 3Solar + storage Β· 2,159 MW Β· agreement signed
- Buttonbush Solar Hybrid Energy CenterSolar + storage Β· 1,636 MW Β· agreement signed
- EuismodSolar + storage Β· 1,247 MW Β· agreement signed
- Bellefield Solar FarmSolar + storage Β· 1,000 MW Β· agreement signed
- Bellefield 2 Solar FarmSolar + storage Β· 1,000 MW Β· agreement signed
- CPC WestWind + storage Β· 750 MW Β· agreement signed
- Buttonbush Solar 2Solar + storage Β· 716 MW Β· agreement signed
- Sanborn Solar 2Solar + storage Β· 707 MW Β· agreement signed
- Willow Rock Energy StorageOther Β· 620 MW Β· agreement signed
- Sanborn 5 HybridSolar Β· 560 MW Β· agreement signed
- Rosamond West SolarSolar + storage Β· 555 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem