🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

GAS · CAISO

Otay Mesa Generating Project

Otay Mesa Generating Project is a 550 MW gas request built and operating in the CAISO interconnection queue, in San Diego County, California, connecting to SDGE.

Queue statusOperating
  1. PlanningQueued Nov 1999 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1A
Grid region
CAISO (California)
Utility / transmission owner
SDGE
Connection point (POI)
Otay Mesa Switchyard 230 kV
Location
San Diego County, California
Technology
Gas: 550 MW
Total requested
550 MW
Study phase
Executed
Queue status
Operational
Entered queue
1 November 1999
Proposed online date
March 2002
Came online
October 2009

Location

Marker shows the centre of San Diego County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Diego County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem