Dracker Solar

Dracker Solar is a 825 MW solar + storage request built and operating in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Jan 2008 (completed)
  2. ConsentedNov 2010 (completed)
  3. Construction (completed)
  4. OperatingTarget Jun 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
294
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Colorado River Substation 220kV
Location
Riverside County, California
Technology
Solar: 485 MW · Battery: 340 MW
Total requested
825 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
16 January 2008
Agreement signed
25 November 2010
Proposed online date
June 2012

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Riverside County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem