Genesis Mccoy

Genesis Mccoy is a 730 MW solar + storage request built and operating in the CAISO interconnection queue, in Riverside County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Apr 2007 (completed)
  2. ConsentedFeb 2011 (completed)
  3. Construction (completed)
  4. OperatingJun 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
193
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Colorado River Substation 500kV
Location
Riverside County, California
Technology
Solar: 500 MW · Battery: 230 MW
Total requested
730 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
4 April 2007
Agreement signed
5 February 2011
Proposed online date
December 2010
Came online
June 2021

Location

Marker shows the centre of Riverside County; the queue data does not give exact sites.