🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA — page 93

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 93 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2023-055, Mayes County
Battery storage
100 MWIn study Mayes, OKSPP Oct 2023target 2028
Solar project J3685, Pike County
Solar
100 MWIn study Pike, ILMISO Apr 2024target 2028
Plano Skies Energy Center
Solar · Plano Skies Energy Center, LLC
100 MWIn study Kendall, ILPJM May 2019target 2022
Solar project J2055, Sheboygan County
Solar
100 MWIn study Sheboygan, WIMISO Aug 2021target 2026
Solar project J3439, Sherburne County
Solar
100 MWIn study Sherburne, MNMISO Apr 2024target 2026
Battery storage project 455, Yellowstone County
Battery storage
100 MWIn study Yellowstone, MTWest Jan 2024target 2028
Solar + storage project 100, Benewah County
Solar + storage
100 MWIn study Benewah, IDWest Sep 2019target 2021
Battery storage project GEN-2022-012, Woodward County
Battery storage
100 MWIn study Woodward, OKSPP Jun 2022target 2028
Solar project J4037, Franklin County
Solar
100 MWIn study Franklin, IAMISO Jun 2025target 2030
Surplus; J909
Other
100 MWIn study Tangipahoa Parish, LAMISO Jan 2025target 2027
Solar project AI1-171, Whiteside County
Solar
100 MWIn study Whiteside, ILPJM Sep 2022target 2028
Battery storage project GEN-2024-359, Stark County
Battery storage
100 MWIn study Stark, NDSPP Mar 2025target 2030
Battery storage project J3162, Rock County
Battery storage
100 MWIn study Rock, WIMISO Sep 2022target 2027
Callisto ID Energy Center
Battery storage · Tempus Power management LLC
100 MWIn study Harris, TXERCOT Oct 2024target 2026
Battery storage project J3160, Fond Du Lac County
Battery storage
100 MWIn study Fond Du Lac, WIMISO Sep 2022target 2027
Battery storage project J3735, Genesee County
Battery storage
100 MWIn study Genesee, MIMISO Apr 2024target 2028
Solar + storage project J3983, Gibson County
Solar + storage
100 MWIn study Gibson, INMISO Oct 2024target 2030
Solar
Solar
100 MWIn study Rockingham, NHISO-NE Jul 2023target 2028
Solar project J2484, Monroe County
Solar
100 MWIn study Monroe, MIMISO Sep 2022target 2025
Riverside Solar
Solar · Riverside Solar, LLC
100 MWIn study Jefferson, NYNYISO Jun 2019target 2027
Solar project 919393, Wake County
Solar · Duke Energy Progress, LLC
100 MWIn study Wake, NCSoutheast Sep 2023
Solar + storage project J1686, Evangeline Parish County
Solar + storage
100 MWIn study Evangeline Parish, LAMISO Jul 2022target 2026
Battery storage project GEN-2022-154, Cleveland County
Battery storage
100 MWIn study Cleveland, OKSPP Feb 2023target 2027
Gas project 07-028, Marion County
Gas
100 MWPaused / redesign Marion, ORWest Oct 2007target 2011
Palmvalley Storage
Battery storage
100 MWPaused / redesign Hidalgo, TXERCOT Sep 2022target 2025
Battery storage project AG2-332, Elkhart County
Battery storage · Amberjack Solar LLC
100 MWIn study Elkhart, INPJM Feb 2025target 2024
Solar + storage project GI-2024-07, Pueblo County
Solar + storage
100 MWIn study Pueblo, COWest May 2024target 2028
Battery storage project T2-041, Multnomah County
Battery storage
100 MWIn study Multnomah, ORWest Sep 2025target 2027
Bear Ridge Solar
Solar · Bear Ridge Solar, LLC
100 MWIn study Niagara, NYNYISO Mar 2018target 2027
Battery storage project AJ1-019, Southampton County
Battery storage
100 MWIn study Southampton, VAPJM Jun 2023target 2028
Battery storage project GI-TC-2024-18, Montezuma County
Battery storage
100 MWIn study Montezuma, COWest May 2024target 2027
Battery storage project 12-054, Clackamas County
Battery storage
100 MWPaused / redesign Clackamas, ORWest Dec 2012target 2014
Battery storage project AI2-005, Fluvanna County
Battery storage
100 MWIn study Fluvanna, VAPJM Oct 2022target 2028
Battery storage project IA-PNM-2019-18, Bernalillo County
Battery storage
100 MWPaused / redesign Bernalillo, NMWest Apr 2019target 2022
Battery storage project 145, Whatcom County
Battery storage
100 MWIn study Whatcom, WAWest Apr 2024target 2027
Solar + storage project 20210310001, Orangeburg County
Solar + storage · May Renewables LLC
100 MWIn study Orangeburg, SCSoutheast target 2026
Solar project J3917, Columbia County
Solar
100 MWIn study Columbia, ARMISO Nov 2024target 2029
Gas project J3156, Rock County
Gas
100 MWIn study Rock, WIMISO Sep 2022target 2026
Solar project J2309, Murray County
Solar
100 MWIn study Murray, MNMISO Sep 2021target 2024
Solar project J2701, Jefferson Davis Parish County
Solar
100 MWIn study Jefferson Davis Parish, LAMISO Sep 2022target 2027
PSE Richardson TX Storage
Battery storage · PureSky Development Inc.
100 MWIn study Hidalgo, TXERCOT Dec 2022target 2027
Headwaters Wind Farm III
Onshore wind
100 MWPaused / redesign Randolph, INPJM Sep 2018target 2026
Battery storage project J3007, Mason County
Battery storage
100 MWIn study Mason, MIMISO Aug 2022target 2025
Battery storage project AH2-126, Jefferson County
Battery storage
100 MWIn study Jefferson, OHPJM Feb 2022target 2026
Mill Point Solar II
Solar + storage · ConnectGen Montgomery County LLC
100 MWIn study Montgomery, NYNYISO Oct 2024target 2028
Battery storage project Company 210, Clark County
Battery storage
100 MWPaused / redesign Clark, NVWest Sep 2021target 2024
Madison County Solar
Solar
100 MWPaused / redesign Madison, INPJM Mar 2018target 2025
Solar project J1534, Olmsted County
Solar
100 MWIn study Olmsted, MNMISO Apr 2025target 2023
Battery storage project C2-204, Yakima County
Battery storage
100 MWIn study Yakima, WAWest May 2022target 2024
Other project GEN-2025-SR19, Chouteau County
Other
100 MWIn study Chouteau, OKSPP Jun 2025target 2029
Page 93 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)