Withdrawn queue requests in the USA — page 92

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 92 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Imperial Solar 1
Solar
280 MWWithdrawn / abandoned Imperial, CACAISO May 2008target 2012
Gas project GEN-2000-003, Moore County
Gas
280 MWWithdrawn / abandoned Moore, TXSPP May 2000
Solar project J2971, Covington County
Solar
280 MWWithdrawn / abandoned Covington, MSMISO Sep 2022target 2026
Gas project 7, Cascade County
Gas
280 MWWithdrawn / abandoned Cascade, MTWest May 2001
Solar project AE1-171, White County
Solar
280 MWWithdrawn / abandoned White, INPJM Sep 2018target 2022
Replacing 100 MW of existing coal generation with 28 Power Electronic 4.01 MVA at Lansing Generation Station; Lansing 4
Other
280 MWWithdrawn / abandoned Allamakee, IAMISO Feb 2022target 2025
Solar project AG2-455, Fountain County
Solar · ALGONQUIN POWER (FOUNTAIN COUNTY SOLAR), LLC
280 MWWithdrawn / abandoned Fountain, INPJM Mar 2021target 2024
Solar project GEN-2023-238, Potter County
Solar
280 MWWithdrawn / abandoned Potter, TXSPP Oct 2023target 2030
Palen Valley Solar 1
Solar
280 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2012
Onshore wind project GI-2004-4, Prowers County
Onshore wind
280 MWWithdrawn / abandoned Prowers, COWest Aug 2004target 2006
Onshore wind project GEN-2022-160, Chaves County
Onshore wind
280 MWWithdrawn / abandoned Chaves, NMSPP Feb 2023target 2028
Suncup
Battery storage
280 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Ludlow Solar 1
Solar
280 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2012
Mccoy Solar 1
Solar
280 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2012
Desert Paintbrush
Battery storage
280 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Other project G216 CONS 110, Livingston County
Other
280 MWWithdrawn / abandoned Livingston, MIMISO Nov 2001target 2004
Onshore wind project CLPT G27, Laramie County
Onshore wind
280 MWWithdrawn / abandoned Laramie, WYWest Jul 2023target 2026
Solar project IC-699, Glynn County
Solar
280 MWWithdrawn / abandoned Glynn, GASoutheast May 2018
Pecan Creek 1 Gas
Gas · NTE Energy
280 MWWithdrawn / abandoned ERCOT Feb 2014target 2019
Solar project IC-773, Burke County
Solar
280 MWWithdrawn / abandoned Burke, GASoutheast Feb 2019
Combined Cycle
Gas
280 MWWithdrawn / abandoned Hampden, MAISO-NE Oct 2006target 2015
LI Cable - Phase 2b
Onshore wind · Long Island Cable, LLC
280 MWWithdrawn / abandoned Suffolk, NYNYISO Apr 2008
Coal project G553, Columbia County
Coal
280 MWWithdrawn / abandoned Columbia, WIMISO Sep 2005target 2007
Coal project G527, Grant County
Coal
280 MWWithdrawn / abandoned Grant, WIMISO Jun 2005target 2006
Onshore wind project 91, Golden Valley County
Onshore wind
280 MWWithdrawn / abandoned Golden Valley, MTWest May 2008target 2013
Gran Vista
Solar + storage
279 MWWithdrawn / abandoned Kern, CACAISO Apr 2011target 2024
Onshore wind project GI-2005-1, Prowers County
Onshore wind
279 MWWithdrawn / abandoned Prowers, COWest Jan 2005target 2006
Gas project 53, Cascade County
Gas
277 MWWithdrawn / abandoned Cascade, MTWest Dec 2006target 2007
Copper MTN Solar 5
Solar + storage
277 MWWithdrawn / abandoned Clark, NVCAISO May 2016target 2023
Solar + storage project J2884, Beauregard Parish County
Solar + storage
276 MWWithdrawn / abandoned Beauregard Parish, LAMISO Sep 2022target 2027
Onshore wind project GI-2018-22, Elbert County
Onshore wind
276 MWWithdrawn / abandoned Elbert, COWest May 2018target 2020
Battery Storage
Battery storage
276 MWWithdrawn / abandoned Suffolk, MAISO-NE Aug 2021target 2023
Battery Storage
Battery storage
275 MWWithdrawn / abandoned Hampden, MAISO-NE Dec 2022target 2027
Coal project G677, Moultrie County
Coal
275 MWWithdrawn / abandoned Moultrie, ILMISO Nov 2008target 2010
Gas project E18, Essex County
Gas
275 MWWithdrawn / abandoned Essex, NJPJM Nov 2000
Other project 18, Payette County
Other
275 MWWithdrawn / abandoned Payette, IDWest Apr 2001target 2005
Other project 17, Washington County
Other
275 MWWithdrawn / abandoned Washington, IDWest Apr 2001target 2005
Onshore wind project GI-2004-3, Weld County
Onshore wind
275 MWWithdrawn / abandoned Weld, COWest Jul 2004target 2006
Oyster shore Energy storage
Battery storage · Shore Rd ESS LLC
275 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2024
Solar project GEN-2023-142, Lamb County
Solar
275 MWWithdrawn / abandoned Lamb, TXSPP Oct 2023target 2029
Johnson County 2
Gas · Brazos Electric Cooperative
275 MWWithdrawn / abandoned ERCOT Dec 2006
Gas project 359, Salt Lake County
Gas
275 MWWithdrawn / abandoned Salt Lake, UTWest Nov 2010target 2014
Solar project 177046, Duplin County
Solar · Masked
275 MWWithdrawn / abandoned Duplin, NCSoutheast May 2021
Solar project 569986, Richmond County
Solar · Masked
275 MWWithdrawn / abandoned Richmond, NCSoutheast Jun 2022
Quail Run Phase III
Gas · Navasota Energy Partners, LP
275 MWWithdrawn / abandoned ERCOT Mar 2007target 2050
Solar + storage project C3-027, Juab County
Solar + storage
275 MWWithdrawn / abandoned Juab, UTWest May 2023target 2026
Onshore wind project GEN-2022-217, Parmer County
Onshore wind
275 MWWithdrawn / abandoned Parmer, TXSPP Mar 2023target 2029
Other project 21, Gooding County
Other
275 MWWithdrawn / abandoned Gooding, IDWest Apr 2001target 2005
Gas Turbine
Gas
275 MWWithdrawn / abandoned Hartford, CTISO-NE Nov 2007target 2010
Solar + storage project C2-37, Juab County
Solar + storage
275 MWWithdrawn / abandoned Juab, UTWest Apr 2022target 2025
Page 92 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)