Solar project IC-773, Burke County

Solar project IC-773, Burke County is a 280 MW solar request withdrawn in the Southeast interconnection queue, in Burke County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2019 (completed)
  2. Withdrawn / abandonedSep 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-773
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Rocky Creek - Wadley Primary 230 kV Line
Location
Burke County, Georgia
Technology
Solar: 280 MW
Total requested
280 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
15 February 2019
Withdrawn
September 2019

Location

Marker shows the centre of Burke County; the queue data does not give exact sites.