United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2023 requests) โ page 9
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project G0890, Lane County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project GEN-2023-212, Bowie County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar project GEN-2023-236, Lea County Solar |
400 MW | Withdrawn / abandoned |
| Onshore wind project G0958, Wasco County Onshore wind |
400 MW | Withdrawn / abandoned |
| Wind + storage project 23-223, Washington County Wind + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project GEN-2023-050, Labette County Solar + storage |
400 MW | Withdrawn / abandoned |
| Other project G0896, Lane County Other |
400 MW | Withdrawn / abandoned |
| Solar + storage project C3-122, Utah County Solar + storage |
400 MW | Withdrawn / abandoned |
| Solar + storage project G0891, Lane County Solar + storage |
400 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2022-208, Andrew County Onshore wind |
400 MW | Withdrawn / abandoned |
| Blue Frost Battery storage ยท Blue Frost Energy Center, LLC |
400 MW | Withdrawn / abandoned |
| Port Jefferson Energy Storage Battery storage ยท Port Jefferson Energy Storage, LLC |
400 MW | Withdrawn / abandoned |
| Solar project 2023-G8 Solar |
400 MW | Withdrawn / abandoned |
| Black Cherry Battery Battery storage ยท Black Cherry Wind Power |
400 MW | Withdrawn / abandoned |
| Other project G0903, Linn County Other |
400 MW | Withdrawn / abandoned |
| Bedias Solar Park Solar ยท Misae Energy III |
400 MW | Withdrawn / abandoned |
| Solar + storage project G0913, Deschutes County Solar + storage |
400 MW | Withdrawn / abandoned |
| Holbrook II Energy Storage Battery storage ยท Holbrook Energy Storage |
400 MW | Withdrawn / abandoned |
| Eastside Plains Energy Center Solar + storage |
393 MW | Withdrawn / abandoned |
| Rancheros Energy Center Solar + storage |
387 MW | Withdrawn / abandoned |
| Solar project GEN-2022-168, Henry County Solar |
380 MW | Withdrawn / abandoned |
| Other project G1005, Klickitat County Other |
380 MW | Withdrawn / abandoned |
| Zoroaster Battery storage |
378 MW | Withdrawn / abandoned |
| Solar project GEN-2022-247, Kidder County Solar |
375 MW | Withdrawn / abandoned |
| DT Solar Solar + storage |
371 MW | Withdrawn / abandoned |
| Solar project GEN-2022-174, Buffalo County Solar |
370 MW | Withdrawn / abandoned |
| Baja Vista Power Bank Battery storage |
370 MW | Withdrawn / abandoned |
| Solar + storage project Company 235, Nye County Solar + storage |
370 MW | Withdrawn / abandoned |
| Other project GEN-2022-112, Hansford County Other |
370 MW | Withdrawn / abandoned |
| Sun Flats Energy Center Solar + storage |
370 MW | Withdrawn / abandoned |
| East Wonder Solar Solar + storage |
368 MW | Withdrawn / abandoned |
| Lock 2 Battery storage |
368 MW | Withdrawn / abandoned |
| Shake Out Solar Solar + storage |
365 MW | Withdrawn / abandoned |
| Socorro Peak Solar 2 Solar + storage |
365 MW | Withdrawn / abandoned |
| Blue Star Solar Solar + storage |
362 MW | Withdrawn / abandoned |
| Solar + storage project Q545, Yavapai County Solar + storage |
360 MW | Withdrawn / abandoned |
| Hiko Battery storage |
360 MW | Withdrawn / abandoned |
| Silver Storage Battery storage |
358 MW | Withdrawn / abandoned |
| Soar Energy Storage Battery storage |
357 MW | Withdrawn / abandoned |
| Melody Battery storage |
354 MW | Withdrawn / abandoned |
| Landmark Battery storage |
353 MW | Withdrawn / abandoned |
| Coyote Flats Energy Center Solar + storage |
351 MW | Withdrawn / abandoned |
| Solar project GEN-2022-221, Wilbarger County Solar |
350 MW | Withdrawn / abandoned |
| Solar + storage project Company PP, Eureka County Solar + storage |
350 MW | Withdrawn / abandoned |
| Battery storage project IA-PNM-2023-25, Bernalillo County Battery storage |
350 MW | Withdrawn / abandoned |
| West Laurens Solar ยท ACE DevCo NC,LLC |
350 MW | Withdrawn / abandoned |
| Solar project GEN-2022-239, Hempstead County Solar |
350 MW | Withdrawn / abandoned |
| Solar project GEN-2022-219, Dawson County Solar |
350 MW | Withdrawn / abandoned |
| Solar + storage project Q501, Pinal County Solar + storage |
350 MW | Withdrawn / abandoned |
| Battery storage project 899003, Chatham County Battery storage ยท Masked |
350 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- CAISO (California)486 ยท 198.6 GW
- West (non-ISO utilities)547 ยท 166.5 GW
- SPP (Southwest Power Pool)336 ยท 71.5 GW
- NYISO (New York)138 ยท 40.7 GW
- Southeast (non-ISO utilities)331 ยท 40.7 GW
- ERCOT (Texas)85 ยท 16.1 GW
- ISO-NE (New England)119 ยท 15.7 GW
- MISO (Midcontinent)10 ยท 1,143 MW
- PJM (Mid-Atlantic, Midwest)11 ยท 867 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)