United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in CAISO (California) — page 9

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown429188.6 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

429 requests · page 9 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Township Power Bank
Battery storage
50.5 MWIn study Sutter, CACAISO Apr 2021target 2028
Verbena Energy Storage
Battery storage
50.5 MWIn study Sutter, CACAISO Apr 2021target 2028
Willow Springs Solar 3
Battery storage
50.0 MWAgreement signed Kern, CACAISO Apr 2014target 2026
Kifer BESS 1
Battery storage
50.0 MWIn study Santa Clara, CACAISO Apr 2021target 2025
Solar Star 4
Solar + storage
50.0 MWAgreement signed Kern, CACAISO May 2016target 2026
North Johnson Energy Center
Battery storage
50.0 MWAgreement signed San Diego, CACAISO Apr 2014target 2026
Chula Vista Energy Center 2
Battery storage
50.0 MWAgreement signed San Diego, CACAISO Apr 2014target 2026
Solar Star 3
Solar + storage
50.0 MWAgreement signed Kern, CACAISO May 2016target 2026
Ares Nevada
Battery storage
44.0 MWAgreement signed Nye, NVCAISO Apr 2014target 2027
Air Station 1
Solar + storage
42.1 MWIn study Kings, CACAISO Apr 2019target 2021
Little Bear 3
Solar + storage
40.4 MWAgreement signed Fresno, CACAISO Apr 20152020
Rio Bravo Solar 1
Solar + storage
40.0 MWAgreement signed Kern, CACAISO Apr 20122016
Kettleman Solar Project (Fka Kettleman Solar Farm)
Solar + storage
40.0 MWAgreement signed Kings, CACAISO May 20102015
Little Bear Solar 1
Solar + storage
40.0 MWAgreement signed Fresno, CACAISO Apr 20142020
Little Bear Solar 2
Solar + storage
40.0 MWAgreement signed Fresno, CACAISO Apr 20142020
Rio Bravo Solar 2
Solar + storage
40.0 MWAgreement signed Kern, CACAISO Apr 20132016
Pumpjack Solar I (Aka Pioneer Solar I)
Solar + storage
40.0 MWAgreement signed Kern, CACAISO Sep 20102015
Crow Creek Solar 1 (Fka: Frontier Solar 1) (Fka As Scatec Westside Solar Ranch I And Stanislaus PV - Phase 1)
Solar + storage
40.0 MWAgreement signed Stanislaus, CACAISO Dec 20092016
Starlight Solar
Solar + storage
37.4 MWAgreement signed San Diego, CACAISO May 2017target 2027
Escondido Energy Center 2
Battery storage
33.0 MWAgreement signed San Diego, CACAISO Apr 2014target 2030
Hidden Knolls BESS
Battery storage
30.8 MWIn study Kern, CACAISO Apr 2021target 2028
Dynamo Solar
Solar
24.5 MWAgreement signed Napa, CACAISO Apr 2019target 2027
Agua Caliente Solar 2
Solar
20.0 MWIn study Maricopa, AZCAISO Mar 2016target 2016
Separator Expansion
Battery storage
12.6 MWIn study San Bernardino, CACAISO Apr 2023target 2025
Lake Alpaugh Battery Storage
Battery storage
10.0 MWAgreement signed Tulare, CACAISO Apr 2015target 2026
Altamont Midway LTD
Onshore wind
5.0 MWAgreement signed Alameda, CACAISO Apr 2015target 2027
Lassen Lodge Hydroelectric
Hydro
4.5 MWAgreement signed Tehama, CACAISO Mar 2011target 2027
Milpa Power Bank
Battery storage
3.0 MWIn study Santa Clara, CACAISO Apr 2018target 2025
Lassen Lodge Hydroelectric 2
Hydro
0.5 MWAgreement signed Tehama, CACAISO Apr 2013target 2027
Page 9 of 9

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)