🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Indiana

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Indiana — page 8

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown579114.4 GW
Active in queue59.6 GW300 requests
Agreement signed11.2 GW69 requests
Withdrawn579114.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

579 requests · page 8 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AH1-484, Henry County
Solar
115 MWWithdrawn / abandoned Henry, INPJM Sep 2021target 2023
Solar project AF2-188, White County
Solar
112 MWWithdrawn / abandoned White, INPJM Mar 2020target 2023
Battery storage project AH1-477, Howard County
Battery storage
112 MWWithdrawn / abandoned Howard, INPJM Sep 2021target 2023
Solar project AH1-014, Huntington County
Solar
112 MWWithdrawn / abandoned Huntington, INPJM Apr 2021target 2024
Solar project AF2-191, St. Joseph County
Solar
110 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2020target 2023
Onshore wind project J2843, Hendricks County
Onshore wind
110 MWWithdrawn / abandoned Hendricks, INMISO Sep 2022target 2025
Solar project J1947, Fountain County
Solar
110 MWWithdrawn / abandoned Fountain, INMISO Mar 2022target 2025
Solar project J3348, Marshall County
Solar
110 MWWithdrawn / abandoned Marshall, INMISO Apr 2024target 2028
Battery storage project AH1-768, Blackford County
Battery storage · RWE Solar Development, LLC
110 MWWithdrawn / abandoned Blackford, INPJM target 2029
Solar + storage project AF2-204, Grant County
Solar + storage
110 MWWithdrawn / abandoned Grant, INPJM Mar 2020target 2023
Solar + storage project AH2-211, St. Joseph County
Solar + storage
110 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2022target 2025
Gas project G940, Gibson County
Gas
105 MWWithdrawn / abandoned Gibson, INMISO Dec 2007target 2008
Onshore wind project G967, Newton County
Onshore wind
101 MWWithdrawn / abandoned Newton, INMISO Jan 2008target 2010
Onshore wind project W2-044, Whitley County
Onshore wind
101 MWWithdrawn / abandoned Whitley, INPJM Jun 2010target 2011
Onshore wind project Y2-010, White County
Onshore wind
100 MWWithdrawn / abandoned White, INPJM May 2012target 2015
Battery storage project J2229, Wabash County
Battery storage
100 MWWithdrawn / abandoned Wabash, INMISO Aug 2021target 2024
Battery storage project J3334, Laporte County
Battery storage
100 MWWithdrawn / abandoned Laporte, INMISO Apr 2024target 2028
Onshore wind project G952, Tipton County
Onshore wind
100 MWWithdrawn / abandoned Tipton, INMISO Jan 2008target 2011
Battery storage project J2255, Ripley County
Battery storage
100 MWWithdrawn / abandoned Ripley, INMISO Aug 2021target 2024
Battery storage project J2408, Switzerland County
Battery storage
100 MWWithdrawn / abandoned Switzerland, INMISO Sep 2022target 2026
Onshore wind project V3-010, Randolph County
Onshore wind
100 MWWithdrawn / abandoned Randolph, INPJM Aug 2009target 2013
Battery storage project J2362, Fountain County
Battery storage
100 MWWithdrawn / abandoned Fountain, INMISO Sep 2022target 2026
Solar project J3196, Starke County
Solar
100 MWWithdrawn / abandoned Starke, INMISO Sep 2022target 2025
Solar project J1680, Cass County
Solar
100 MWWithdrawn / abandoned Cass, INMISO Jun 2020target 2023
Solar project AG1-006, Jay County
Solar
100 MWWithdrawn / abandoned Jay, INPJM Apr 2020target 2023
Esker Solar Park II
Solar · Headwaters Wind Farm III LLC d/b/a Esker Solar Park LLC and Esker Solar Park II LLC
100 MWWithdrawn / abandoned Delaware, INPJM Sep 2020target 2024
Solar project J2216, Vigo County
Solar
100 MWWithdrawn / abandoned Vigo, INMISO Apr 2022target 2024
Michiana Solar
Solar · ibV Energy Partners LLC
100 MWWithdrawn / abandoned St. Joseph, INPJM Jan 2025target 2025
Battery storage project AH1-413, Allen County
Battery storage
100 MWWithdrawn / abandoned Allen, INPJM Sep 2021target 2025
Solar project J2221, Clark County
Solar
100 MWWithdrawn / abandoned Clark, INMISO Aug 2021target 2025
Solar project J3244, Parke County
Solar
100 MWWithdrawn / abandoned Parke, INMISO Mar 2024target 2028
Solar project J1385, Hendricks County
Solar
100 MWWithdrawn / abandoned Hendricks, INMISO Apr 2019target 2022
Onshore wind project J1116, Hancock County
Onshore wind
100 MWWithdrawn / abandoned Hancock, INMISO Mar 2018target 2021
Onshore wind project U2-091, Randolph County
Onshore wind
100 MWWithdrawn / abandoned Randolph, INPJM Jul 2008target 2011
Solar project J1694, Lawrence County
Solar
100 MWWithdrawn / abandoned Lawrence, INMISO Jun 2020target 2024
Solar project J1624, Bartholomew County
Solar
100 MWWithdrawn / abandoned Bartholomew, INMISO Jun 2020target 2024
Solar project AG1-424, Allen County
Solar · Leeward Renewable Energy Development, LLC
100 MWWithdrawn / abandoned Allen, INPJM Sep 2020target 2023
Solar project AD1-139, Madison County
Solar
100 MWWithdrawn / abandoned Madison, INPJM Sep 2017target 2020
Solar + storage project AG2-116, White County
Solar + storage · Honey Creek Energy, LLC
100 MWWithdrawn / abandoned White, INPJM Jan 2021target 2023
Battery storage project J2722, Clinton County
Battery storage
100 MWWithdrawn / abandoned Clinton, INMISO Sep 2022target 2026
Battery storage project AH1-301, Allen County
Battery storage
100 MWWithdrawn / abandoned Allen, INPJM Sep 2021target 2025
Battery storage project J2281, White County
Battery storage
100 MWWithdrawn / abandoned White, INMISO Aug 2021target 2024
Solar project AG2-574, Allen County
Solar
100 MWWithdrawn / abandoned Allen, INPJM Mar 2021target 2023
Battery storage project J3290, White County
Battery storage
100 MWWithdrawn / abandoned White, INMISO Apr 2024target 2028
Battery storage project J2329, Vigo County
Battery storage
100 MWWithdrawn / abandoned Vigo, INMISO Sep 2022target 2025
Battery storage project J3813, Putnam County
Battery storage
100 MWWithdrawn / abandoned Putnam, INMISO Apr 2024target 2028
Blackford County Solar
Solar · Blackford County Wind Farm LLC d/b/a Blackford County Solar Park LLC
100 MWWithdrawn / abandoned Blackford, INPJM Sep 2020target 2024
Battery storage project J2263, Knox County
Battery storage
100 MWWithdrawn / abandoned Knox, INMISO Aug 2021target 2024
Onshore wind project G571, Clinton County
Onshore wind
100 MWWithdrawn / abandoned Clinton, INMISO Nov 2005target 2011
Solar project J2206, Fountain County
Solar
100 MWWithdrawn / abandoned Fountain, INMISO Aug 2021target 2025
Page 8 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)